18232 W HARTLAND ST 91335

Certificate Information: 18232 W HARTLAND ST 91335

Application / Permit
20016-20000-01939
Plan Check / Job No.
B20VN01063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
RE-SLAB DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 ALDOUS CHIC
Corrections Issued 1/23/2020 ALDOUS CHIC
Plan Check Approved 3/10/2020 SARKIS HARABEDIAN
Issued 3/11/2020 LADBS
CofO in Progress 8/23/2021 MICHAEL SMITH
CofO Issued 8/23/2021 MICHAEL SMITH
Permit Finaled 8/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/23/2020 GUILLERMO PETRA
Sewer availability Cleared 1/23/2020 GUILLERMO PETRA
Construction within easement Cleared 3/9/2020 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/10/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/2/2020 Approved VINCENT HANLEY
PLUMBING-Rough 4/2/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/14/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/7/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/7/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 5/7/2020 Approved VINCENT HANLEY
Drywall Nailing 5/13/2020 Approved VINCENT HANLEY
Green Building Rough 5/13/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/18/2020 Approved VINCENT HANLEY
Final 7/13/2020 Corrections Issued VINCENT HANLEY
Green Building Final 7/13/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 7/13/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 7/17/2020 Approved VINCENT HANLEY
Final 7/17/2020 Corrections Issued VINCENT HANLEY
HVAC-Final 7/17/2020 Approved VINCENT HANLEY
PLUMBING-Final 7/17/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/17/2020 SGSOV Approved VINCENT HANLEY
ELECTRICAL-Final 8/6/2021 Approved VINCENT HANLEY
Final 8/6/2021 Corrections Issued VINCENT HANLEY
Gas Test 8/6/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/6/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/6/2021 SGSOV Approved VINCENT HANLEY
Final 8/23/2021 OK to Issue CofO MICHAEL SMITH