4933 N MORELLA AVE 91607

Certificate Information: 4933 N MORELLA AVE 91607

Application / Permit
20016-20000-01894
Plan Check / Job No.
B20VN01030
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 35' X 24' 10" DETACHED IRR.-SHAPE RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 6/3/2020
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 GURUNATH NESARAJAH
Corrections Issued 1/23/2020 GURUNATH NESARAJAH
Plan Check Approved 3/3/2020 GURUNATH NESARAJAH
Issued 6/3/2020 APPLICANT
Building Plans Picked Up 6/5/2020 APPLICANT
CofO in Progress 7/12/2022 DAVID MATSON
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/28/2020 GUILLERMO PETRA
Sewer availability Cleared 1/28/2020 GUILLERMO PETRA
ZA Case Cleared 1/30/2020 DAISY BENICIA
ZA Case Cleared 1/30/2020 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 2/21/2020 APEKSHYA BAJRACHARYA
Specific Plan Cleared 3/4/2020 MARIANNE KING

Contact Information

Contractor Scales Zerik; Lic. No.: 1012586-B 4922 WEST BLVD      LOS ANGELES, CA 90043

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/17/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/17/2020 Not Ready for Inspection THOMAS FINNILA
Wood Frame 6/17/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 7/22/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/28/2020 Not Ready for Inspection THOMAS FINNILA
Insulation 8/28/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/28/2020 Partial Approval THOMAS FINNILA
Wood Frame 8/28/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/4/2020 Partial Inspection THOMAS FINNILA
Insulation 9/4/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/4/2020 Approved THOMAS FINNILA
Wood Frame 9/4/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/22/2020 Partial Approval THOMAS FINNILA
Insulation 9/22/2020 Partial Approval THOMAS FINNILA
PLUMBING-Rough 9/22/2020 Partial Approval THOMAS FINNILA
Wood Frame 9/22/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Not Ready for Inspection THOMAS FINNILA
Insulation 10/15/2020 Partial Approval THOMAS FINNILA
Shower Pan 10/15/2020 Approved THOMAS FINNILA
Wood Frame 10/15/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/16/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/16/2020 Partial Approval THOMAS FINNILA
Drywall Nailing 10/21/2020 Approved THOMAS FINNILA
ELECTRICAL-Final 12/11/2020 Not Ready for Inspection THOMAS FINNILA
Final 12/11/2020 Corrections Issued THOMAS FINNILA
Final 2/17/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 2/17/2021 Approved THOMAS FINNILA
Final 7/12/2022 OK to Issue CofO DAVID MATSON