6611-6613 N DE CELIS PL 91406

Certificate Information: 6611-6613 N DE CELIS PL 91406

Application / Permit
20016-20000-01627
Plan Check / Job No.
B20VN00877
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2020 ALDOUS CHIC
Corrections Issued 1/21/2020 ALDOUS CHIC
Plan Check Approved 5/1/2020 PINANK PATEL
Issued 5/28/2020 LADBS
CofO in Progress 12/19/2020 MICHAEL TEMPLE
CofO Issued 12/26/2020 MICHAEL SMITH
Permit Finaled 12/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/22/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/22/2020 GUILLERMO PETRA
Sewer availability Cleared 1/22/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2020 Approved MARK JOHNSON
Underground Mechanical 6/2/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/8/2020 Approved WILLIAM KUEHN
Gas Test 6/8/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 6/8/2020 Approved WILLIAM KUEHN
Insulation 6/12/2020 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 6/12/2020 Corrections Issued GREGG CUMMINGS
Insulation 6/16/2020 Approved DANIEL DREW
Interior/Exterior Lathing 6/16/2020 Approved DANIEL DREW
Drywall Nailing 7/1/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 9/24/2020 Approved ARAM AVEDISIAN
Final 9/24/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/24/2020 Approved ARAM AVEDISIAN
Green Building Rough 9/24/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/24/2020 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/24/2020 Approved ARAM AVEDISIAN
Wood Frame 9/29/2020 Conditional Approval BRENDAN LOONEY
Final 12/21/2020 OK to Issue CofO MICHAEL TEMPLE
Special/Order Compliance 12/21/2020 Approved MICHAEL TEMPLE