238 S MCCADDEN PL 90004

Certificate Information: 238 S MCCADDEN PL 90004

Application / Permit
20016-20000-01506
Plan Check / Job No.
B20VN00822
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19' X 36'6" DETACHED THREE CAR GARAGE TO ACCESSORY DWELLING UNIT AS PER AB 494 AND SB 229, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/17/2020 RARES BODEA
Corrections Issued 1/21/2020 RARES BODEA
Building Plans Picked Up 2/5/2020 APPLICANT
Applicant returned to address corrections 3/11/2020 RARES BODEA
Plan Check Approved 3/12/2020 RARES BODEA
Issued 3/12/2020 LADBS
CofO in Progress 12/4/2020 JOSEPH MCGARRY
Permit Finaled 12/4/2020 DEROLD HAUFF
CofO Issued 12/4/2020 DEROLD HAUFF
Permit Finaled 12/4/2020 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 2/13/2020 SUKI GERSHENHORN
HPOZ Cleared 2/13/2020 SUKI GERSHENHORN
Address approval Cleared 3/11/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/11/2020 GABRIEL ROBLES
Sewer availability Cleared 3/11/2020 GABRIEL ROBLES

Contact Information

Contractor Lannen Construction Inc; Lic. No.: 811038-B 5841 AIRDROME ST      LOS ANGELES, CA 90019
Engineer Samara,, Muzahim Ali; Lic. No.: C26015 9100 S SEPULVEDA BLVD SUITE 115      LOS ANGELES, CA 90045

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2020 Partial Approval ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 5/4/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 5/19/2020 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 6/12/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 6/12/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 6/19/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 6/19/2020 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/30/2020 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 6/30/2020 Approved ARTHUR SARGSYAN
Insulation 7/2/2020 Approved ARTHUR SARGSYAN
Insulation 7/8/2020 Approved ARTHUR SARGSYAN
Wood Frame 7/8/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 7/10/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/10/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 11/18/2020 Corrections Issued SCOTT FINNILA
Final 11/18/2020 Corrections Issued SCOTT FINNILA
Green Building Final 11/18/2020 Approved SCOTT FINNILA
HVAC-Final 11/18/2020 Corrections Issued SCOTT FINNILA
METHANE-Final 11/18/2020 Approved SCOTT FINNILA
PLUMBING-Final 11/18/2020 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Approved SCOTT FINNILA
Smoke Detectors 11/18/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 12/2/2020 Approved JOSEPH MCGARRY
Final 12/2/2020 OK to Issue CofO JOSEPH MCGARRY
HVAC-Final 12/2/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 12/2/2020 Approved JOSEPH MCGARRY