20935 W CHASE ST 91304

Certificate Information: 20935 W CHASE ST 91304

Application / Permit
20016-20000-01485
Plan Check / Job No.
B20VN00802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20'-4" X 20'-9" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ENGINEERING
Permit Issued
Issued on 8/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/22/2020 JENNIFER LEE
Corrections Issued 1/22/2020 JENNIFER LEE
Applicant returned to address corrections 3/24/2020 ALDOUS CHIC
Plan Check Approved 7/20/2020 JEROME MAGAT PALMA
Issued 8/7/2020 APPLICANT
CofO in Progress 6/10/2022 CHRIS CHRISTENSEN
CofO Issued 6/15/2022 JOHN JANSON
Permit Finaled 6/15/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/4/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/4/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/5/2020 ADRIAN CASTRO
"T" removal Cleared 7/14/2020 SARAHI ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Avila,, Albert Guerrero; Lic. No.: C41726 10034 GLADE AVNENUE      CHATSWORTH, CA 91311

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/13/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 8/13/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 8/13/2020 Corrections Issued DAVID STEPANYAN
Gas Test 8/13/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 8/13/2020 Corrections Issued DAVID STEPANYAN
Pre-Inspection 8/13/2020 Partial Inspection DAVID STEPANYAN
Footing/Foundation/Slab 3/16/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 7/27/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 7/27/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 3/25/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/25/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 3/25/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 3/25/2022 Approved CHRIS CHRISTENSEN
Insulation 3/25/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/25/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/6/2022 Approved JESUS PINEDA
Final 5/31/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/31/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/31/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 6/6/2022 Approved JESUS PINEDA
Final 6/9/2022 OK to Issue CofO CHRIS CHRISTENSEN