20935 W CHASE ST 91304
Certificate Information: 20935 W CHASE ST 91304
- Application / Permit
- 20016-20000-01485
- Plan Check / Job No.
- B20VN00802
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20'-4" X 20'-9" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ENGINEERING
- Permit Issued
- Issued on 8/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | JENNIFER LEE |
| Corrections Issued | 1/22/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 3/24/2020 | ALDOUS CHIC |
| Plan Check Approved | 7/20/2020 | JEROME MAGAT PALMA |
| Issued | 8/7/2020 | APPLICANT |
| CofO in Progress | 6/10/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 6/15/2022 | JOHN JANSON |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/4/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | ADRIAN CASTRO |
| "T" removal | Cleared | 7/14/2020 | SARAHI ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/13/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/13/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/13/2020 | Corrections Issued | DAVID STEPANYAN |
| Gas Test | 8/13/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 8/13/2020 | Corrections Issued | DAVID STEPANYAN |
| Pre-Inspection | 8/13/2020 | Partial Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 3/16/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/27/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 7/27/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/6/2022 | Approved | JESUS PINEDA |
| Final | 5/31/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/6/2022 | Approved | JESUS PINEDA |
| Final | 6/9/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |