426 S SERRANO AVE 90020

Certificate Information: 426 S SERRANO AVE 90020

Application / Permit
20016-20000-01433
Plan Check / Job No.
B20VN00772
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 9' 8" X 21' 6" BALCONY DECK, REMOVE & REPLACE (2) 5' 1" DIAMETER SPIRAL STAIRS AND MAJOR INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 7/21/2020
Issuing Office
Valley
Current Status
Permit Finaled on 9/22/2021

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 GURUNATH NESARAJAH
Corrections Issued 1/25/2020 GURUNATH NESARAJAH
Quality Review Completed 1/28/2020 STEVEN KIM
Building Plans Picked Up 1/29/2020 APPLICANT
Plan Check Approved 3/18/2020 GURUNATH NESARAJAH
Issued 7/21/2020 APPLICANT
Permit Finaled 9/22/2021 JOSEPH MCGARRY

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/3/2020 EMIL KYUPELYAN
Hist. Property Cntrct Mgr Appr Cleared 2/24/2020 LAMBERT GIESSINGER
Historic monument Cleared 2/24/2020 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 3/18/2020 GABRIEL ROBLES
Sewer availability Cleared 3/18/2020 GABRIEL ROBLES

Contact Information

Architect Chun,, Youngmin; Lic. No.: C32890 1828 LINCOLN BLVD #B      SANTA MONICA, CA 90404
Contractor S M X Development; Lic. No.: 1027521-B 3579 E FOOTHILL BLVD #280      PASADENA, CA 91107
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/26/2020 Conditional Approval CHRIS CHRISTENSEN
Pre-Inspection 8/26/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/18/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/18/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 3/18/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/18/2021 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 3/18/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/6/2021 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/6/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/6/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/6/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/6/2021 Approved CHRIS CHRISTENSEN
Insulation 4/16/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/16/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 5/6/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/6/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/20/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 9/20/2021 Approved ARTHUR SARGSYAN
Final 9/20/2021 Corrections Issued ARTHUR SARGSYAN
HVAC-Final 9/20/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 9/20/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 9/20/2021 Approved ARTHUR SARGSYAN
Final 9/22/2021 Permit Finaled JOSEPH MCGARRY
Service/Power Release 9/22/2021 Approved JOSEPH MCGARRY