22737-22739 W HAMLIN ST 91307

Certificate Information: 22737-22739 W HAMLIN ST 91307

Application / Permit
20016-20000-01360
Plan Check / Job No.
B20VN00742
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 2/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 ALDOUS CHIC
Corrections Issued 1/16/2020 ALDOUS CHIC
Applicant returned to address corrections 2/21/2020 MARVEL DELACRUZ
Issued 2/21/2020 LADBS
CofO in Progress 2/15/2022 TROY SANDERS
Permit Finaled 2/18/2022 JOHN JANSON
CofO Issued 2/18/2022 JOHN JANSON
Permit Finaled 2/18/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/17/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/17/2020 GABRIEL ROBLES
Sewer availability Cleared 1/17/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2020 Partial Approval TROY SANDERS
Deputy Drilled-In Anchors 6/30/2020 Approved TROY SANDERS
Footing/Foundation/Slab 7/2/2020 Approved TROY SANDERS
ELECTRICAL-Rough 1/27/2021 Approved TROY SANDERS
PLUMBING-Rough 1/27/2021 Approved TROY SANDERS
Insulation 7/19/2021 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 7/19/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/26/2021 Approved HENRY KIM
Drywall Nailing 7/26/2021 Approved HENRY KIM
Green Building Rough 7/26/2021 Approved HENRY KIM
HVAC-Rough 7/26/2021 Corrections Issued HENRY KIM
Shower Pan 8/3/2021 Approved TROY SANDERS
Interior/Exterior Lathing 8/9/2021 Partial Approval STEPHANIE SWANSON
Final 12/27/2021 Corrections Issued TROY SANDERS
Green Building Final 12/27/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Approved TROY SANDERS
Service/Power Release 12/27/2021 Approved TROY SANDERS
Smoke Detectors 12/27/2021 Approved TROY SANDERS
Final 2/14/2022 OK to Issue CofO TROY SANDERS
Green Building Final 2/14/2022 Approved TROY SANDERS