22737-22739 W HAMLIN ST 91307
Certificate Information: 22737-22739 W HAMLIN ST 91307
- Application / Permit
- 20016-20000-01360
- Plan Check / Job No.
- B20VN00742
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | ALDOUS CHIC |
| Corrections Issued | 1/16/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 2/21/2020 | MARVEL DELACRUZ |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 2/15/2022 | TROY SANDERS |
| Permit Finaled | 2/18/2022 | JOHN JANSON |
| CofO Issued | 2/18/2022 | JOHN JANSON |
| Permit Finaled | 2/18/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/17/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/9/2020 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 6/30/2020 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 7/2/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 1/27/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/27/2021 | Approved | TROY SANDERS |
| Insulation | 7/19/2021 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/19/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | HENRY KIM |
| Drywall Nailing | 7/26/2021 | Approved | HENRY KIM |
| Green Building Rough | 7/26/2021 | Approved | HENRY KIM |
| HVAC-Rough | 7/26/2021 | Corrections Issued | HENRY KIM |
| Shower Pan | 8/3/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | STEPHANIE SWANSON |
| Final | 12/27/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 12/27/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 12/27/2021 | Approved | TROY SANDERS |
| Smoke Detectors | 12/27/2021 | Approved | TROY SANDERS |
| Final | 2/14/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/14/2022 | Approved | TROY SANDERS |