1363 W BRAMPTON ROAD 90041

Certificate Information: 1363 W BRAMPTON ROAD 90041

Application / Permit
20016-20000-00806
Plan Check / Job No.
B20VN00431
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSED 11' 7.5" X 4'8.5" BALCONY TO BEDROOM AND REMODEL TO (E) SFD W/ GARAGE PER ENGINEER.
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 PINANK PATEL
Corrections Issued 1/10/2020 PINANK PATEL
Building Plans Picked Up 1/13/2020 APPLICANT
Plan Check Approved 1/30/2020 PINANK PATEL
Issued 2/25/2020 LADBS
CofO in Progress 5/7/2021 CRAIG VAUGHAN
Permit Finaled 6/14/2022 DEROLD HAUFF
CofO Issued 6/14/2022 DEROLD HAUFF
Permit Finaled 6/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/30/2020 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 8/5/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/5/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 8/5/2020 Corrections Issued CRAIG VAUGHAN
Insulation 8/5/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 8/5/2020 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 8/5/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/17/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 8/17/2020 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 8/17/2020 Partial Approval CRAIG VAUGHAN
Smoke Detectors 8/17/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 8/20/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/20/2020 Approved CRAIG VAUGHAN
HVAC-Rough 8/20/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/20/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/26/2020 Approved CRAIG VAUGHAN
HVAC-Rough 8/26/2020 Corrections Issued CRAIG VAUGHAN
MERV13>=Rough 8/26/2020 Approved CRAIG VAUGHAN
Insulation 8/28/2020 Approved CRAIG VAUGHAN
Drywall Nailing 9/2/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/16/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/23/2020 Corrections Issued CRAIG VAUGHAN
Final 3/16/2021 Corrections Issued CRAIG VAUGHAN
MERV13>=Final 3/16/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/16/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 3/16/2021 Approved CRAIG VAUGHAN
Final 4/1/2021 Corrections Issued CRAIG VAUGHAN
Final 4/16/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 5/6/2021 Approved CRAIG VAUGHAN
Final 5/6/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 5/6/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 5/6/2021 Approved CRAIG VAUGHAN