3824 N SUNBEAM DR 90065

Certificate Information: 3824 N SUNBEAM DR 90065

Application / Permit
20016-20000-00798
Plan Check / Job No.
B20VN00421
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 6'-4" X 16' (109 sq.ft) COVERED PORCH INTO (N) ENTRY AND BATHROOM.
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 RAPHAEL ROSAS
Corrections Issued 1/10/2020 RAPHAEL ROSAS
Plan Check Approved 2/21/2020 ALDO UBAU
Issued 2/24/2020 LADBS
CofO in Progress 12/1/2020 HAMIK HARTOUNIAN
Permit Finaled 12/2/2020 DEROLD HAUFF
CofO Issued 12/2/2020 DEROLD HAUFF
Permit Finaled 12/2/2020 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 2/20/2020 OLGA RUANO
ZI Cleared 2/20/2020 OLGA RUANO

Contact Information

Contractor B H Remodeling; Lic. No.: 1036402-B 7849 AURA AVENUE      RESEDA, CA 91335

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2020 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 3/2/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 3/12/2020 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 3/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 6/3/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/25/2020 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 6/25/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/30/2020 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/6/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/6/2020 Approved HAMIK HARTOUNIAN
Insulation 7/6/2020 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/6/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/9/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Gas Test 7/9/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/9/2020 Partial Approval CHRISTOPHER DELLEFIELD
Final 7/28/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 7/28/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/4/2020 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 8/4/2020 Approved HAMIK HARTOUNIAN
Final 9/14/2020 Conditional Approval ENRIQUE MIRELES
Final 11/30/2020 OK to Issue CofO HAMIK HARTOUNIAN