14082 W AZTEC ST 91342

Certificate Information: 14082 W AZTEC ST 91342

Application / Permit
20016-20000-00785
Plan Check / Job No.
B20VN00412
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' x 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 2/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 ROSENDO MEDINA
Corrections Issued 1/14/2020 ROSENDO MEDINA
Building Plans Picked Up 1/14/2020 APPLICANT
Plan Check Approved 2/12/2020 ROSENDO MEDINA
Issued 2/18/2020 LADBS
CofO in Progress 4/26/2021 MISAEL ESPARZA
CofO Issued 6/24/2021 MICHAEL SMITH
Permit Finaled 6/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Permit Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 1/27/2020 JOHN KIM

Contact Information

Contractor Carlos Enrique Munoz; Lic. No.: 908224-B 2027 PHILLIPPI STREET      SAN FERNANDO, CA 91340
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2020 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 9/16/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/16/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Approved JENNIFER RABUCHIN
Gas Test 9/16/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/16/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 9/16/2020 Corrections Issued JENNIFER RABUCHIN
Sewer 9/16/2020 Approved JENNIFER RABUCHIN
Insulation 9/24/2020 Partial Approval MISAEL ESPARZA
Insulation 10/19/2020 Approved MISAEL ESPARZA
Drywall Nailing 10/23/2020 Approved MISAEL ESPARZA
Green Building Rough 10/23/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/23/2020 Approved MISAEL ESPARZA
Shower Pan 10/29/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 1/20/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/20/2021 Not Ready for Inspection MISAEL ESPARZA
Final 1/20/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 1/20/2021 Approved MISAEL ESPARZA
Green Building Final 1/20/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 1/20/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/20/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/20/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 1/20/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/4/2021 No Access for Inspection MISAEL ESPARZA
Final 2/4/2021 No Access for Inspection MISAEL ESPARZA
Green Building Final 2/4/2021 No Access for Inspection MISAEL ESPARZA
HVAC-Final 2/4/2021 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 2/4/2021 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/4/2021 SGSOV Not Ready MISAEL ESPARZA
ELECTRICAL-Final 2/11/2021 Approved MISAEL ESPARZA
HVAC-Final 2/11/2021 Approved MISAEL ESPARZA
Final 3/8/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/8/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/8/2021 Not Ready for Inspection MISAEL ESPARZA
Sewer 3/8/2021 Approved MISAEL ESPARZA
Final 4/26/2021 OK to Issue CofO MISAEL ESPARZA
PLUMBING-Final 4/26/2021 Approved MISAEL ESPARZA