6625 1/2 W WILLOUGHBY AVE 90038
Certificate Information: 6625 1/2 W WILLOUGHBY AVE 90038
- Application / Permit
- 20016-20000-00542
- Plan Check / Job No.
- B20VN00269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ALTERATION to convert Garage to irregular 13'x18' Recreation Room and an irregular 9.5'x18' (exterior access only) Storage. SEE COMMENTS.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | LUIS RINCON |
| Corrections Issued | 1/10/2020 | LUIS RINCON |
| Applicant returned to address corrections | 2/14/2020 | LUIS RINCON |
| Applicant returned to address corrections | 5/8/2020 | LUIS RINCON |
| Applicant returned to address corrections | 5/26/2020 | LUIS RINCON |
| Plan Check Approved | 6/1/2020 | LUIS RINCON |
| No Progress | 11/4/2020 | LUIS RINCON |
| Plan Check Approved | 2/22/2021 | LUIS RINCON |
| Issued | 3/24/2021 | APPLICANT |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| CofO in Progress | 8/2/2022 | BRIAN SULLIVAN |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
| CofO Issued | 2/7/2023 | DEROLD HAUFF |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/27/2021 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 9/2/2021 | Partial Approval | RAUL BARAJAS |
| Insulation | 9/2/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Drywall Nailing | 9/10/2021 | Approved | RAUL BARAJAS |
| Insulation | 9/10/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/15/2021 | Approved | RAUL BARAJAS |
| Final | 6/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| METHANE-Final | 6/10/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/10/2022 | Approved | BRIAN SULLIVAN |
| Final | 8/1/2022 | OK to Issue CofO | BRIAN SULLIVAN |