7623-7625 N MINSTREL AVE 91304

Certificate Information: 7623-7625 N MINSTREL AVE 91304

Application / Permit
20016-20000-00530
Plan Check / Job No.
B20VN00259
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert the attached garage into an Accessory Dwelling Unit per AB 494 & SB 229
Permit Issued
Issued on 1/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2020 ANGELICA DAVE
Corrections Issued 1/8/2020 ANGELICA DAVE
Plan Check Approved 1/8/2020 PINANK PATEL
Issued 1/13/2020 LADBS
CofO in Progress 8/24/2020 DAVID STEPANYAN
Permit Finaled 8/25/2020 JOHN JANSON
CofO Issued 8/25/2020 JOHN JANSON
Permit Finaled 8/25/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/8/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/8/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/8/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2020 Approved PETER FOLLING
PLUMBING-Rough 1/29/2020 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 2/13/2020 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 2/13/2020 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 2/13/2020 Approved PETER FOLLING
BUILDING-Rough-Frame 3/16/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 3/16/2020 Corrections Issued DAVID STEPANYAN
Green Building Rough 3/16/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 3/16/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 4/7/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 4/7/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 4/7/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 4/7/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 5/5/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 5/5/2020 Approved DAVID STEPANYAN
Insulation 5/5/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 5/18/2020 Approved DAVID STEPANYAN
Drywall Nailing 5/18/2020 Approved DAVID STEPANYAN
Shower Pan 5/18/2020 Approved DAVID STEPANYAN
Gas Test 6/3/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/3/2020 Approved DAVID STEPANYAN
Final 8/12/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 8/12/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 8/12/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/24/2020 Approved DAVID STEPANYAN
Final 8/24/2020 OK to Issue CofO DAVID STEPANYAN
HVAC-Final 8/24/2020 Approved DAVID STEPANYAN
PLUMBING-Final 8/24/2020 Approved DAVID STEPANYAN