1340-1342 S HAUSER BLVD 90019

Certificate Information: 1340-1342 S HAUSER BLVD 90019

Application / Permit
20016-20000-00289
Plan Check / Job No.
B20VN00155
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 1/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 ALDOUS CHIC
Corrections Issued 1/6/2020 ALDOUS CHIC
Plan Check Approved 1/9/2020 PINANK PATEL
Issued 1/14/2020 LADBS
CofO in Progress 12/15/2020 DAVID CHAN
Permit Finaled 6/24/2021 DEROLD HAUFF
CofO Issued 6/24/2021 DEROLD HAUFF
Permit Finaled 6/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/6/2020 GUILLERMO PETRA
Sewer availability Cleared 1/6/2020 GUILLERMO PETRA

Contact Information

Contractor M R D Construction; Lic. No.: 960463-B 13719 VENTURA BLVD UNIT D      SHERMAN OAKS, CA 91423

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2020 Partial Approval MATTHEW NUCKOLLS
PLUMBING-Rough 1/31/2020 Partial Approval MATTHEW NUCKOLLS
Footing/Foundation/Slab 2/4/2020 Approved MATTHEW NUCKOLLS
ELECTRICAL-Rough 3/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 3/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/10/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 4/10/2020 Corrections Issued DAVID CHAN
Wood Frame 4/10/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 4/21/2020 Conditional Approval DAVID CHAN
PLUMBING-Rough 4/21/2020 Approved DAVID CHAN
Shower Pan 4/21/2020 Approved DAVID CHAN
Insulation 5/6/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 5/6/2020 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 5/19/2020 Approved DAVID CHAN
Insulation 5/19/2020 Approved DAVID CHAN
Wood Frame 5/19/2020 Approved DAVID CHAN
Drywall Nailing 5/27/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 10/19/2020 Approved DAVID CHAN
ELECTRICAL-Final 10/19/2020 Approved DAVID CHAN
Final 10/19/2020 Corrections Issued DAVID CHAN
Green Building Final 10/19/2020 Approved DAVID CHAN
Green Building Rough 10/19/2020 Approved DAVID CHAN
METHANE-Final 10/19/2020 Approved DAVID CHAN
METHANE-Rough 10/19/2020 Approved DAVID CHAN
PLUMBING-Final 10/19/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved DAVID CHAN
Smoke Detectors 10/19/2020 Approved DAVID CHAN
Final 12/14/2020 OK to Issue CofO DAVID CHAN
HVAC-Final 12/14/2020 Approved DAVID CHAN
Service/Power Release 12/14/2020 Approved DAVID CHAN