22225 W ARCHWOOD ST 91303

Certificate Information: 22225 W ARCHWOOD ST 91303

Application / Permit
20016-20000-00225
Plan Check / Job No.
B20VN00127
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 JEROME MAGAT PALMA
Corrections Issued 1/7/2020 JEROME MAGAT PALMA
Building Plans Picked Up 1/9/2020 APPLICANT
Plan Check Approved 1/17/2020 JEROME MAGAT PALMA
Issued 1/17/2020 LADBS
CofO in Progress 7/15/2020 MICHAEL TEMPLE
CofO in Progress 7/15/2020 MICHAEL SMITH
CofO Issued 7/15/2020 MICHAEL SMITH
Permit Finaled 7/15/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/16/2020 ADRIAN CASTRO
Sewer availability Cleared 1/16/2020 ADRIAN CASTRO
Construction near power lines Cleared 1/17/2020 OSCAR CASTRO
ZI Cleared 1/17/2020 HERMINIGILDO AGUSTIN
Hold Cleared 1/28/2020 LOURDES RAMIRO

Contact Information

Contractor La Renovators; Lic. No.: 974391-B 300 MIKE LOZA APT 111      CAMARILLO, CA 93012

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 2/4/2020 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 2/4/2020 Approved JOHN KIDWELL
PLUMBING-Rough 2/4/2020 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/18/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 2/18/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 2/18/2020 Approved JOHN KIDWELL
Green Building Rough 2/18/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 3/4/2020 Not Ready for Inspection JOHN KIDWELL
Insulation 3/4/2020 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 3/4/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/4/2020 Not Ready for Inspection JOHN KIDWELL
Drywall Nailing 3/6/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 3/6/2020 Not Ready for Inspection JOHN KIDWELL
Insulation 3/6/2020 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 3/6/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/6/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 3/13/2020 Approved JOHN KIDWELL
HVAC-Rough 3/13/2020 Not Ready for Inspection JOHN KIDWELL
Insulation 3/13/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/13/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 3/18/2020 Approved JOHN KIDWELL
HVAC-Rough 3/18/2020 Corrections Issued JOHN KIDWELL
Insulation 3/18/2020 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 3/18/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/18/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/20/2020 Approved JOHN KIDWELL
ELECTRICAL-Rough 3/20/2020 Approved JOHN KIDWELL
Green Building Rough 3/20/2020 Approved JOHN KIDWELL
HVAC-Rough 3/20/2020 Approved JOHN KIDWELL
Insulation 3/20/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/20/2020 Partial Approval JOHN KIDWELL
Drywall Nailing 3/24/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/24/2020 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 4/9/2020 Partial Approval JOHN KIDWELL
Shower Pan 4/9/2020 Approved JOHN KIDWELL
Gas Test 5/14/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/14/2020 Partial Approval JOHN KIDWELL
Sewer 5/14/2020 Approved JOHN KIDWELL
Gas Test 5/18/2020 Approved JOHN KIDWELL
PLUMBING-Rough 5/18/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 5/20/2020 Not Ready for Inspection JOHN KIDWELL
Final 5/20/2020 Not Ready for Inspection JOHN KIDWELL
Gas Test 5/20/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Final 5/20/2020 Approved JOHN KIDWELL
HVAC-Final 5/20/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 5/20/2020 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/20/2020 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 5/20/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 5/22/2020 Approved JOHN KIDWELL
Final 5/22/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 5/22/2020 Approved JOHN KIDWELL
PLUMBING-Final 5/22/2020 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/22/2020 SGSOV Not Ready JOHN KIDWELL
Final 5/28/2020 OK to Issue CofO JOHN KIDWELL
PLUMBING-Final 5/28/2020 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/28/2020 SGSOV Approved JOHN KIDWELL