10413-10415 N BLUCHER AVE 91344

Certificate Information: 10413-10415 N BLUCHER AVE 91344

Application / Permit
20016-20000-00164
Plan Check / Job No.
B20VN00098
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 1/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 ANGELICA DAVE
Corrections Issued 1/3/2020 ANGELICA DAVE
Plan Check Approved 1/9/2020 JEFFREY TANGONAN
Issued 1/9/2020 LADBS
CofO in Progress 7/10/2020 MARK JOHNSON
CofO Issued 7/20/2020 MICHAEL SMITH
Permit Finaled 7/20/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/3/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/3/2020 GUILLERMO PETRA
Sewer availability Cleared 1/3/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/10/2020 Not Ready for Inspection MARK JOHNSON
Underground Mechanical 3/10/2020 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 3/16/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 3/16/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 3/27/2020 Corrections Issued MARK JOHNSON
Gas Test 3/27/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 3/27/2020 Approved MARK JOHNSON
PLUMBING-Rough 3/27/2020 Approved MARK JOHNSON
Wood Frame 3/27/2020 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 4/1/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 4/1/2020 Approved MARK JOHNSON
Green Building Rough 4/1/2020 Approved MARK JOHNSON
HVAC-Rough 4/1/2020 Approved MARK JOHNSON
MERV13>=Rough 4/1/2020 Approved MARK JOHNSON
Insulation 4/6/2020 Approved MARK JOHNSON
Drywall Nailing 4/10/2020 Approved MARK JOHNSON
ELECTRICAL-Final 4/22/2020 Corrections Issued JENNIFER RABUCHIN
Final 4/22/2020 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 4/22/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/22/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/22/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 4/22/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/22/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/22/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/22/2020 Approved JENNIFER RABUCHIN
Final 5/12/2020 Partial Approval MARK JOHNSON
Green Building Final 5/12/2020 Approved MARK JOHNSON
Final 7/10/2020 OK to Issue CofO MARK JOHNSON