18806 W WELBY WAY 91335

Certificate Information: 18806 W WELBY WAY 91335

Application / Permit
20016-20000-00099
Plan Check / Job No.
B20VN00054
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to Accessory Dwelling Unit
Permit Issued
Issued on 1/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 ANGELICA DAVE
Corrections Issued 1/3/2020 ANGELICA DAVE
Issued 1/10/2020 LADBS
CofO in Progress 10/14/2020 VINCENT HANLEY
Permit Finaled 10/20/2020 DONALD SUNSERI
CofO Issued 10/20/2020 DONALD SUNSERI
Permit Finaled 10/20/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 1/7/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/7/2020 GABRIEL ROBLES
Sewer availability Cleared 1/7/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2020 Approved VINCENT HANLEY
Sewer 4/24/2020 Partial Approval VINCENT HANLEY
Underground Mechanical 4/24/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/27/2020 Corrections Issued VINCENT HANLEY
HVAC-Rough 5/27/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 5/27/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 6/3/2020 Approved VINCENT HANLEY
PLUMBING-Rough 6/3/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/5/2020 Approved VINCENT HANLEY
Green Building Rough 6/5/2020 Approved VINCENT HANLEY
Insulation 6/5/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/5/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 6/17/2020 Approved VINCENT HANLEY
HVAC-Rough 6/17/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/17/2020 Approved VINCENT HANLEY
Shower Pan 6/17/2020 Approved VINCENT HANLEY
Final 8/21/2020 Corrections Issued DAVID SCANTLIN
Green Building Final 8/21/2020 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Approved DAVID SCANTLIN
Sewer 8/21/2020 Approved DAVID SCANTLIN
Smoke Detectors 8/21/2020 Approved DAVID SCANTLIN
ELECTRICAL-Final 9/28/2020 Approved VINCENT HANLEY
Final 9/28/2020 Corrections Issued VINCENT HANLEY
Green Building Final 9/28/2020 Approved VINCENT HANLEY
HVAC-Final 9/28/2020 Approved VINCENT HANLEY
PLUMBING-Final 9/28/2020 Approved VINCENT HANLEY
Final 10/14/2020 OK to Issue CofO VINCENT HANLEY