1005 N LILLIAN WAY 90038

Certificate Information: 1005 N LILLIAN WAY 90038

Application / Permit
20016-10002-24650
Plan Check / Job No.
B21LA05778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Motion Picture Production
Work Description
Supplemental to 20016-10001-24650: CHANGE OF USE FROM WAREHOUSE TO MEDIA PRODUCTION STUDIO
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
CofO Issued on 11/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 HERNAN ARREOLA
Corrections Issued 4/7/2021 HERNAN ARREOLA
Quality Review Completed 4/13/2021 JASON HEALEY
Applicant returned to address corrections 4/30/2021 HERNAN ARREOLA
Applicant returned to address corrections 6/9/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/9/2021 HERNAN ARREOLA
Plan Check Approved 8/4/2021 HERNAN ARREOLA
Issued 9/3/2021 APPLICANT
Building Plans Picked Up 9/8/2021 APPLICANT
CofO in Progress 11/4/2021 SORIN CIRSTOIU
CofO in Progress 11/4/2021 SORIN CIRSTOIU
CofO Issued 11/12/2021 ERNESTO CORRAL
Permit Finaled 11/12/2021 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 4/30/2021 JOE LUCKEY
ZI Cleared 4/30/2021 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 5/4/2021 RENZ SORIANO
Sewer availability Cleared 5/4/2021 RENZ SORIANO
Prkng lot landscape/Water mgmt Cleared 5/17/2021 JOE LUCKEY
Fire Marshal Fire Life Safety Cleared 5/25/2021 VIDAL GARCIA

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 9/21/2021 Approved JONATHAN QUACH
Deputy Drilled-In Anchors 9/30/2021 Conditional Approval JONATHAN QUACH
Final 10/12/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 10/12/2021 Partial Inspection SORIN CIRSTOIU
Smoke Detectors 10/12/2021 Approved SORIN CIRSTOIU
Final 10/28/2021 Conditional Approval SORIN CIRSTOIU
Reinforced Masonry Frame 10/28/2021 Approved SORIN CIRSTOIU
Final 11/4/2021 OK to Issue CofO SORIN CIRSTOIU