816 1/2 S SPAULDING AVE 90036

Certificate Information: 816 1/2 S SPAULDING AVE 90036

Application / Permit
20016-10001-33527
Plan Check / Job No.
B22LA13445
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Supplemental permit to 21014-10000-02208 to change scope from Addition to New ADU per City Ordinance.
Permit Issued
Issued on 10/26/2022
Issuing Office
Current Status
Permit Finaled on 9/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/13/2022 RICARDO RAMIREZ
Corrections Issued 7/14/2022 RICARDO RAMIREZ
Applicant returned to address corrections 8/31/2022 RICARDO RAMIREZ
Applicant returned to address corrections 10/14/2022 RICARDO RAMIREZ
Plan Check Approved 10/26/2022 RICARDO RAMIREZ
Issued 10/26/2022 APPLICANT
Permit Finaled 9/26/2023 SCOTT FINNILA

Permit Application Clearance Information

HPOZ Cleared 9/6/2022 CHRISTINA PARK
Miscellaneous Cleared 9/6/2022 CHRISTINA PARK
ZI Cleared 9/6/2022 CHRISTINA PARK
Miscellaneous Cleared 10/11/2022 CHRISTINA PARK

Contact Information

Contractor C P R Builders Inc; Lic. No.: 1058058-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/1/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 2/2/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 2/7/2023 Partial Approval RICHARD DOCKUS
Sewer 2/7/2023 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 2/14/2023 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/7/2023 Corrections Issued RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 3/10/2023 Approved RICHARD DOCKUS
Masonry Wall/Backfill 3/23/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/6/2023 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 4/11/2023 Partial Approval RICHARD DOCKUS
METHANE-Rough 4/11/2023 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 4/11/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/2/2023 Corrections Issued RICHARD DOCKUS
Gas Test 6/2/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/2/2023 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 6/8/2023 Approved JEFFREY MEAD
Insulation 6/15/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 6/22/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/27/2023 Corrections Issued RICHARD DOCKUS
Green Building Rough 6/27/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/30/2023 Approved RICHARD DOCKUS
Insulation 6/30/2023 Approved RICHARD DOCKUS
Drywall Nailing 7/13/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/13/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/19/2023 Partial Approval STUART CHAPMAN
Final 8/28/2023 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 8/28/2023 Approved ROY SPAULDING
Green Building Final 8/28/2023 Approved ROY SPAULDING
METHANE-Barrier 8/28/2023 Approved ROY SPAULDING
METHANE-Subgrade 8/28/2023 Approved ROY SPAULDING
Service/Power Release 8/28/2023 Approved ROY SPAULDING
Smoke Detectors 8/28/2023 Approved ROY SPAULDING
Final 9/26/2023 Permit Finaled SCOTT FINNILA