1701 W ADAMS BLVD 90018
Certificate Information: 1701 W ADAMS BLVD 90018
- Application / Permit
- 20016-10001-32676
- Plan Check / Job No.
- B23LA15157
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Laundry Plant
- Work Description
- SUPPLEMENTAL TO PERMIT # 20016-10000-32676 TO REVISE THE PLANS: CHANGE THE HEIGHT OF BUILDING FROM 21' TO 25'& CHANGE STRUCTURE FORM MASONRY TO STEEL FRAME BUILDING.( FIRE DAMGED REPAIR & MAJOR REMODEL TO (E) LAUNDRY BUILDING .( FIRE DAMAGED (40%) AT REAR PORTION OF BUILDING ) ( no change to floor area).
- Permit Issued
- Issued on 11/13/2023
- Issuing Office
- Metro
- Current Status
- Issued on 11/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | GARO TELMI |
| Corrections Issued | 8/29/2023 | GARO TELMI |
| Quality Review Completed | 8/30/2023 | KEN GILL |
| Building Plans Picked Up | 9/5/2023 | APPLICANT |
| Green Plans Picked Up | 9/27/2023 | APPLICANT |
| Applicant returned to address corrections | 9/28/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/24/2023 | GARO TELMI |
| Plan Check Approved | 11/9/2023 | GARO TELMI |
| Issued | 11/13/2023 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 8/31/2023 | AARON COSTA |
| Community Plan Implem. Overlay | Cleared | 9/8/2023 | MOHAMMAD HASAN |
| Community Plan Implem. Overlay | Cleared | 9/11/2023 | ADALBERTO VERA |
| DAS Clearance | Cleared | 9/12/2023 | GARO TELMI |
| ZA Case | Cleared | 9/13/2023 | RYAN LY |
| ZA Case | Cleared | 9/13/2023 | RYAN LY |
| ZA Case | Cleared | 9/13/2023 | RYAN LY |
| Community Plan Implem. Overlay | Cleared | 9/14/2023 | JEANIE LAM |
| Highway dedication | Cleared | 9/14/2023 | JEANIE LAM |
| Low Impact Development | Cleared | 9/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 9/14/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2023 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 9/19/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 9/19/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 9/29/2023 | TORI CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Esparza,, Jesus Toncks; Lic. No.: C19990 | 6107 YORK BLVD LOS ANGELES, CA 90042 |
| Engineer | Orikura,, Masaaki; Lic. No.: C71338 | 800 ASPIRATIONS CT MODESTO, CA 95356 |
| Engineer | Rowlands,, James; Lic. No.: C21818 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/29/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 11/30/2023 | Partial Approval | MARTIN TAVITIAN |
| Deputy Drilled-In Anchors | 12/6/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Partial Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 1/25/2024 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 4/29/2024 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Partial Approval | ALFREDO LOPEZ |
| Pre-Inspection | 8/29/2024 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 9/27/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/15/2024 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 10/25/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Smoke Detectors | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Special/Order Compliance | 10/30/2024 | Corrections Issued | ALFREDO LOPEZ |
| Wood Frame | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/1/2024 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 11/12/2024 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/26/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 12/3/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 12/4/2024 | Partial Approval | JEROME BLACKWOOD |
| Pre-Inspection | 12/4/2024 | Partial Inspection | NICK DANERI |
| Special/Order Compliance | 12/4/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 1/29/2025 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 2/3/2025 | Corrections Issued | DARRYL ARNOLD |
| Drywall Nailing | 2/5/2025 | Partial Approval | ALFREDO LOPEZ |