3456 S MOORE ST 90066

Certificate Information: 3456 S MOORE ST 90066

Application / Permit
20016-10001-26396
Plan Check / Job No.
B21LA01525
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 20016-10000-26396: CHANGE SCOPE TO ADDITION AND MAJOR REMODEL OF 2-STORY SFD. STRUCTURAL CHANGES AND ADDITIONS TO ENLARGE THE SECOND FLOOR. UNDERPIN (E) FOUNDATION.FULLY SPRINKLERED.
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 JESSE JIMENEZ
Corrections Issued 2/17/2021 JESSE JIMENEZ
Building Plans Picked Up 2/18/2021 APPLICANT
Plan Check Approved 3/19/2021 SAMUEL GONZALEZ
Issued 3/19/2021 APPLICANT
CofO in Progress 8/15/2022 BOBBY KEY
Permit Finaled 8/23/2022 DANIEL ORRANTE
CofO Issued 8/23/2022 DANIEL ORRANTE
Permit Finaled 8/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 3/2/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/5/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/5/2021 DINAH GARIN
Grading Pre-Inspection Cleared 3/17/2021 JESSE JIMENEZ

Contact Information

Architect Anderson,, Robert James; Lic. No.: C13654 85 BELL CANYON ROAD      BELL CANYON, CA 91307
Contractor Anderson Robert Construction; Lic. No.: 861662-B 18169 KNOLL HILL      GRANADA HILLS, CA 91344
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/24/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/22/2021 Partial Approval JESUS RODRIGUEZ
Green Building Rough 7/22/2021 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 8/3/2021 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 8/23/2021 Approved JUAN VALENZUELA
Sewer 8/23/2021 Approved JUAN VALENZUELA
Underground Mechanical 8/23/2021 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Corrections Issued ENRIQUE MIRELES
Green Building Rough 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 9/2/2021 Partial Approval ENRIQUE MIRELES
Green Building Rough 9/2/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 9/2/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 9/14/2021 Approved ENRIQUE MIRELES
HVAC-Rough 9/14/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/30/2021 Partial Approval MORRIS JACKSON
Gas Test 10/8/2021 Approved ENRIQUE MIRELES
Insulation 10/8/2021 Approved ENRIQUE MIRELES
Shower Pan 10/8/2021 Approved ENRIQUE MIRELES
Drywall Nailing 10/15/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/8/2021 Corrections Issued JOHN KAYON
Gas Test 12/10/2021 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 6/1/2022 Approved PATRICK QUALEY
Green Building Rough 6/1/2022 Approved PATRICK QUALEY
HVAC-Final 6/1/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 6/1/2022 Corrections Issued PATRICK QUALEY
Service/Power Release 6/1/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 6/6/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 6/6/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Final 6/6/2022 Not Ready for Inspection PATRICK QUALEY
Service/Power Release 6/6/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 6/13/2022 Approved PATRICK QUALEY
PLUMBING-Final 6/13/2022 Approved PATRICK QUALEY
Final 6/17/2022 Corrections Issued PATRICK QUALEY
Green Building Final 6/17/2022 Approved PATRICK QUALEY
HVAC-Final 6/17/2022 Approved PATRICK QUALEY
Smoke Detectors 6/17/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 8/15/2022 Approved BOBBY KEY
Final 8/15/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 8/15/2022 Approved BOBBY KEY
PLUMBING-Final 8/15/2022 Approved BOBBY KEY