2236 S GUTHRIE DR 90034
Certificate Information: 2236 S GUTHRIE DR 90034
- Application / Permit
- 20016-10001-05023
- Plan Check / Job No.
- B20LA15037
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **BACK ROOM SUPPLEMENTAL PERMIT** SUPPLEMENTAL TO 20016-10000-05023 TO ADD A BALCONY AT 2ND FLOOR, AND A DECK AT THE REAR OF EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | JOHNNY WU |
| Corrections Issued | 8/21/2020 | JOHNNY WU |
| Applicant returned to address corrections | 8/31/2020 | JOHNNY WU |
| Applicant returned to address corrections | 9/18/2020 | JOHNNY WU |
| Applicant returned to address corrections | 10/2/2020 | JOHNNY WU |
| Plan Check Approved | 10/28/2020 | JOHNNY WU |
| Issued | 10/28/2020 | APPLICANT |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2020 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 10/27/2020 | DINAH GARIN |
Contact Information
| Contractor | Harari Construction Inc; Lic. No.: 1017539-B | 9719 OAKMORE ROAD LOS ANGELES, CA 90035 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Approved | KEVIN SARGSYAN |
| Wood Frame | 2/3/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 9/29/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/29/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 9/30/2022 | Conditional Approval | MICHAEL PELHAM |