SUPPLEMENT TO PERMIT # 20016-10000-02190 TO CAPTURE MEP FEES.
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
Permit Finaled on 7/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Issued 1/5/2021 APPLICANT
Permit Finaled 7/19/2022 ANTHONY EGSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Pro Construction Inc; Lic. No.: 1028385-B 861 N HAMILTON BLVD      POMONA, CA 91768

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/7/2021 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 1/7/2021 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 1/7/2021 Partial Approval DAVID CHAN
PLUMBING-Rough 1/7/2021 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 4/15/2021 No Access for Inspection DAVID FEILER
ELECTRICAL-Rough 4/15/2021 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 4/15/2021 No Access for Inspection DAVID FEILER
PLUMBING-Rough 4/15/2021 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 4/26/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 4/26/2021 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 4/26/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 4/26/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 6/15/2021 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 6/15/2021 Partial Inspection DAVID FEILER
PLUMBING-Rough 6/15/2021 Partial Inspection DAVID FEILER
Wood Frame 6/15/2021 Partial Inspection DAVID FEILER
PLUMBING-Rough 9/29/2021 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 9/30/2021 Approved HORACE FULTZ
BUILDING-Rough-Frame 1/6/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/6/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 1/6/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/16/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 2/16/2022 Corrections Issued ANTHONY EGSON
HVAC-Rough 2/16/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 2/24/2022 Approved ANTHONY EGSON
Insulation 2/24/2022 Not Ready for Inspection ANTHONY EGSON
Insulation 3/2/2022 Approved ANTHONY EGSON
Drywall Nailing 3/11/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 3/11/2022 Not Ready for Inspection HORACE FULTZ
Interior/Exterior Lathing 3/15/2022 Approved ANTHONY EGSON
Service/Power Release 5/11/2022 Approved ANTHONY EGSON
Final 7/19/2022 Permit Finaled ANTHONY EGSON