6528 N RHODES AVE 91606

Certificate Information: 6528 N RHODES AVE 91606

Application / Permit
20016-10000-33582
Plan Check / Job No.
B20LA24278
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE EXISTING PATIO COVER AND CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33 (c)-(d). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 1/11/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 JOE VO
Corrections Issued 1/13/2021 JOE VO
Applicant returned to address corrections 2/2/2021 MONICA RAMIREZ
Applicant returned to address corrections 5/11/2022 JESSE JIMENEZ
Plan Check Approved 8/18/2022 GEORGE ALVAREZ
Plan Check Approved 1/11/2023 GEORGE ALVAREZ
Issued 1/11/2023 APPLICANT
CofO in Progress 6/24/2025 GAREN HAYRAPETYAN
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/25/2021 MATTHEW CRAIG
Construction near power lines Cleared 6/10/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 6/16/2022 ROSE MARIE SMITH
Low Impact Development Cleared 8/17/2022 CHRIS VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/30/2024 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 2/7/2024 Approved JOSE AVILA
Footing/Foundation/Slab 2/7/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 2/9/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 3/18/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/20/2024 Corrections Issued JOSE AVILA
HVAC-Rough 3/20/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/20/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Approved JOSE AVILA
PLUMBING-Rough 4/2/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 4/9/2024 Approved JOSE AVILA
Interior/Exterior Lathing 4/9/2024 Approved JOSE AVILA
MERV13>=Rough 4/9/2024 Approved JOSE AVILA
Shower Pan 4/9/2024 Approved JOSE AVILA
Insulation 4/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 4/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/9/2024 Approved SALVADOR MARTINEZ
Shower Pan 5/9/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 12/27/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 12/27/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 12/27/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 12/27/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/16/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 1/16/2025 Approved GAREN HAYRAPETYAN
Final 1/16/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/16/2025 Approved GAREN HAYRAPETYAN
Green Building Final 1/16/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 1/16/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 1/16/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 1/16/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 1/16/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved GAREN HAYRAPETYAN
Final 6/24/2025 OK to Issue CofO GAREN HAYRAPETYAN