1319 E MONO ST 90033
Certificate Information: 1319 E MONO ST 90033
- Application / Permit
- 20016-10000-33513
- Plan Check / Job No.
- B20LA24216
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR TENANT IMPROVEMENT: DEMOLITION OF NON LOAD BEARING WALLS & (E) MEZZANINE AND PREPARE AREA FOR THE ADDITION OF (2) NEW COMPLIANT GENDER NEUTRAL RESTROOMS & NEW MANDOOR AT (E) WAREHOUSE.
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- Issued on 4/16/2021
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/5/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/15/2021 | TSE MING HUANG |
| Issued | 4/16/2021 | APPLICANT |
| Building Plans Picked Up | 4/27/2021 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/12/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 1/25/2021 | DAVID URITA |
Contact Information
| Architect | Simon,, Matthew Evans; Lic. No.: C29326 | 3956 GUNDRY AVENUE LONG BEACH, CA 90807 |
| Contractor | Wilson Norm & Sons Inc; Lic. No.: 435700-B | 3400 EAST SPRING STREET LONG BEACH, CA 908062430 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/24/2021 | Approved | LANNY MERRICK |
| Deputy Reinf. Concrete | 8/25/2021 | Conditional Approval | LANNY MERRICK |
| Light Gage Steel Frame | 10/27/2021 | Conditional Approval | DANIEL COLLINS |
| Final | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| METHANE-Final | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| METHANE-Rough | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| Reinforced Masonry Frame | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| Final | 12/13/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| METHANE-Final | 12/13/2021 | Approved | BRUCE CAMPBELL |
| METHANE-Rough | 12/13/2021 | Approved | BRUCE CAMPBELL |
| Reinforced Masonry Frame | 12/13/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Not Required | BRUCE CAMPBELL |
| Smoke Detectors | 12/13/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 12/30/2021 | Partial Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 3/29/2022 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 4/12/2022 | Conditional Approval | MARK FERRARI |
| Final | 6/9/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Reinforced Masonry Frame | 6/9/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 6/16/2022 | Corrections Issued | MARK FERRARI |
| Reinforced Masonry Frame | 6/16/2022 | Approved | MARK FERRARI |