1319 E MONO ST 90033

Certificate Information: 1319 E MONO ST 90033

Application / Permit
20016-10000-33513
Plan Check / Job No.
B20LA24216
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR TENANT IMPROVEMENT: DEMOLITION OF NON LOAD BEARING WALLS & (E) MEZZANINE AND PREPARE AREA FOR THE ADDITION OF (2) NEW COMPLIANT GENDER NEUTRAL RESTROOMS & NEW MANDOOR AT (E) WAREHOUSE.
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
Issued on 4/16/2021

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/5/2021 FARSHAD ALIMOHAMADI
Corrections Issued 1/5/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 3/15/2021 TSE MING HUANG
Issued 4/16/2021 APPLICANT
Building Plans Picked Up 4/27/2021 APPLICANT

Permit Application Clearance Information

Historic Resource Verification Cleared 1/12/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 1/25/2021 DAVID URITA

Contact Information

Architect Simon,, Matthew Evans; Lic. No.: C29326 3956 GUNDRY AVENUE      LONG BEACH, CA 90807
Contractor Wilson Norm & Sons Inc; Lic. No.: 435700-B 3400 EAST SPRING STREET      LONG BEACH, CA 908062430

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/24/2021 Approved LANNY MERRICK
Deputy Reinf. Concrete 8/25/2021 Conditional Approval LANNY MERRICK
Light Gage Steel Frame 10/27/2021 Conditional Approval DANIEL COLLINS
Final 12/1/2021 Not Ready for Inspection MARK FERRARI
METHANE-Final 12/1/2021 Not Ready for Inspection MARK FERRARI
METHANE-Rough 12/1/2021 Not Ready for Inspection MARK FERRARI
Reinforced Masonry Frame 12/1/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Not Ready MARK FERRARI
Smoke Detectors 12/1/2021 Not Ready for Inspection MARK FERRARI
Final 12/13/2021 Not Ready for Inspection BRUCE CAMPBELL
METHANE-Final 12/13/2021 Approved BRUCE CAMPBELL
METHANE-Rough 12/13/2021 Approved BRUCE CAMPBELL
Reinforced Masonry Frame 12/13/2021 Not Ready for Inspection BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Not Required BRUCE CAMPBELL
Smoke Detectors 12/13/2021 Approved BRUCE CAMPBELL
Wood Frame 12/30/2021 Partial Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 3/29/2022 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 4/12/2022 Conditional Approval MARK FERRARI
Final 6/9/2022 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 6/9/2022 Not Ready for Inspection KATY RAMIREZ
Final 6/16/2022 Corrections Issued MARK FERRARI
Reinforced Masonry Frame 6/16/2022 Approved MARK FERRARI