3519-3521 W CARNATION AVE 90026
Certificate Information: 3519-3521 W CARNATION AVE 90026
- Application / Permit
- 20016-10000-33463
- Plan Check / Job No.
- B20LA24187
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT CARPORT/GARAGE AND PORTION OF (E) DWELLING TO CREATE ADU
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | HERNAN ARREOLA |
| Corrections Issued | 1/29/2021 | HERNAN ARREOLA |
| Quality Review Completed | 2/3/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Plan Check Approved | 5/21/2021 | HERNAN ARREOLA |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 10/23/2023 | THOMAS LOGRASSO |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
| CofO Issued | 10/24/2023 | DEROLD HAUFF |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2021 | ROSA SILVA |
| Address approval | Cleared | 2/17/2021 | ROSA SILVA |
| Sewer availability | Cleared | 2/18/2021 | THOMAS LANG |
Contact Information
| Contractor | Handcrafted Construction Inc; Lic. No.: 841160-B | 5408 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/9/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/9/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/9/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/9/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 8/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/15/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 9/15/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/15/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/15/2021 | Approved | THOMAS LOGRASSO |
| Sewer | 11/17/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 11/29/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/18/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 1/31/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 1/31/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 1/31/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 1/31/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 2/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 2/17/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 2/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 2/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Service/Power Release | 2/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/22/2022 | Approved | THOMAS LOGRASSO |
| Final | 3/22/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 3/22/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 3/22/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 3/22/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 3/28/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/23/2023 | OK to Issue CofO | THOMAS LOGRASSO |