7538 N GAVIOTA AVE 91406

Certificate Information: 7538 N GAVIOTA AVE 91406

Application / Permit
20016-10000-33426
Plan Check / Job No.
B20LA24154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing Garage into new ADU w/ ground floor addition.
Permit Issued
Issued on 3/24/2021
Issuing Office
Current Status
CofO Issued on 8/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2021 JOE VO
Corrections Issued 1/10/2021 JOE VO
Quality Review Completed 1/22/2021 MINYE PAK
Applicant returned to address corrections 3/14/2021 JOE VO
Plan Check Approved 3/18/2021 JOE VO
Issued 3/24/2021 APPLICANT
CofO in Progress 8/20/2021 JACK KARGODORIAN
Permit Finaled 8/24/2021 MICHAEL SMITH
CofO Issued 8/24/2021 MICHAEL SMITH
Permit Finaled 8/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/19/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/19/2021 GABRIEL ROBLES
Sewer availability Cleared 1/19/2021 GABRIEL ROBLES
Construction near power lines Cleared 1/20/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/20/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2021 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/31/2021 Approved JENNIFER RABUCHIN
Gas Test 3/31/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/31/2021 Partial Approval JENNIFER RABUCHIN
Sewer 3/31/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 3/31/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/27/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/27/2021 Approved ARTHUR SARGSYAN
Green Building Rough 4/27/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 4/27/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/27/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/5/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 5/5/2021 Approved DAVID SCANTLIN
Insulation 5/7/2021 Approved MORRIS JACKSON
Pre-Inspection 5/7/2021 Partial Inspection ALIZAH MAYAGOITIA
Drywall Nailing 5/12/2021 Approved ARTHUR SARGSYAN
Final 7/7/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 7/7/2021 Approved JACK KARGODORIAN
HVAC-Final 7/7/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 7/7/2021 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/7/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 7/7/2021 Approved JACK KARGODORIAN
Final 7/23/2021 Partial Inspection JACK KARGODORIAN
Final 8/2/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 8/20/2021 Approved JACK KARGODORIAN
Final 8/20/2021 OK to Issue CofO JACK KARGODORIAN
HVAC-Final 8/20/2021 Approved JACK KARGODORIAN
PLUMBING-Final 8/20/2021 Approved JACK KARGODORIAN