533 S SERRANO AVE 90020
Certificate Information: 533 S SERRANO AVE 90020
- Application / Permit
- 20016-10000-33412
- Plan Check / Job No.
- B20LA24141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (3) SPECIAL CANTILEVERED COLUMNS WITH STEEL GRADE BEAMS.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofC Issued on 3/12/2024
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | JESSE VIDUYA |
| Corrections Issued | 1/26/2021 | JESSE VIDUYA |
| Quality Review Completed | 1/29/2021 | DAVID CHANG |
| Applicant returned to address corrections | 2/10/2021 | JESSE VIDUYA |
| Plan Check Approved | 3/3/2021 | JESSE VIDUYA |
| Issued | 3/25/2021 | APPLICANT |
| OK for CofC | 5/26/2021 | DARRYL ARNOLD |
| CofC Issued | 3/12/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/3/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 2/22/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 3/25/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Steel/Welding | 4/23/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 4/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/6/2021 | Approved | DARRYL ARNOLD |
| Reinforced Concrete Frame | 5/6/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 5/6/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/6/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/17/2021 | Approved | MARK FERRARI |
| Final | 5/26/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/26/2021 | Approved | DARRYL ARNOLD |