6527 S CRENSHAW BLVD 90043
Certificate Information: 6527 S CRENSHAW BLVD 90043
- Application / Permit
- 20016-10000-33407
- Plan Check / Job No.
- B20LA24138
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- ROOFTOP SOLAR PANNEL PREHEATING SYSTEM
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/28/2022
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | AUNG SOE |
| Corrections Issued | 1/19/2021 | AUNG SOE |
| Quality Review Completed | 1/26/2021 | HERNAN ARREOLA |
| Building Plans Picked Up | 3/30/2021 | APPLICANT |
| Plan Check Approved | 8/3/2021 | AUNG SOE |
| Issued | 8/13/2021 | APPLICANT |
| Permit Finaled | 6/27/2022 | JAMES POWERS |
Permit Application Clearance Information
| CPC | Cleared | 3/31/2021 | MAXFIELD VERMY |
| CPC | Cleared | 3/31/2021 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 3/31/2021 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 3/31/2021 | MAXFIELD VERMY |
| City owned building/parcel | Cleared | 4/1/2021 | REVERDIA TRAMMELL |
| Redevelopment Project Area | Cleared | 4/13/2021 | DAVID URITA |
| "D" conditions | Cleared | 4/22/2021 | DENZEL HENDERSON |
| Specific Plan | Cleared | 4/23/2021 | KYLE WINSTON |
| Metro Rail approval | Cleared | 5/13/2021 | AUNG SOE |
Contact Information
| Contractor | Promise Energy Inc; Lic. No.: 978353-B | 3558 ROUND BARN BLVD SUITE 200 SANTA ROSA, CA 95403 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 6/21/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Not Ready | TIMOTHY BUXTON |
| Smoke Detectors | 6/21/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 6/27/2022 | Permit Finaled | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 6/27/2022 | Approved | JAMES POWERS |