9445 W KIRKSIDE ROAD 90035

Certificate Information: 9445 W KIRKSIDE ROAD 90035

Application / Permit
20016-10000-33399
Plan Check / Job No.
B20LA24132
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 KEVIN MORALES
Corrections Issued 12/30/2020 KEVIN MORALES
Applicant returned to address corrections 1/22/2021 KEVIN MORALES
Applicant returned to address corrections 2/9/2021 MONICA RAMIREZ
Plan Check Approved 7/27/2021 KEVIN MORALES
Issued 8/10/2021 APPLICANT
CofO in Progress 5/3/2022 KEVIN SARGSYAN
Permit Finaled 5/21/2022 DANIEL ORRANTE
CofO Issued 5/21/2022 DANIEL ORRANTE
Permit Finaled 5/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/7/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 1/8/2021 ANTHONY MAINEZ
Sewer availability Cleared 1/8/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 1/12/2021 PATRICK MISCHLICH
Construction within easement Cleared 3/10/2021 RIDWAN HARDY

Contact Information

Contractor Arrow Construction & Remodeling Inc; Lic. No.: 718685-B 1749 SOUTH SHERBOURNE DRIVE      LOS ANGELES, CA 90035
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2021 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 10/6/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/14/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/18/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 10/28/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/10/2021 Partial Approval EVAN COOPER
Green Building Rough 12/10/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 12/10/2021 Not Ready for Inspection EVAN COOPER
Wood Frame 12/10/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/7/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 1/7/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 1/7/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 1/7/2022 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 1/7/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/7/2022 Corrections Issued KEVIN SARGSYAN
Wood Frame 1/7/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 2/1/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 2/1/2022 Approved KEVIN SARGSYAN
HVAC-Rough 2/1/2022 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 2/1/2022 Partial Approval KEVIN SARGSYAN
METHANE-Rough 2/1/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 2/1/2022 Not Ready for Inspection KEVIN SARGSYAN
Sewer 2/1/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 2/4/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/4/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/4/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 2/4/2022 Approved KEVIN SARGSYAN
Insulation 2/8/2022 Corrections Issued KEVIN SARGSYAN
Gas Test 4/20/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 4/20/2022 Approved KEVIN SARGSYAN
Drywall Nailing 5/3/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 5/3/2022 Approved KEVIN SARGSYAN
Final 5/3/2022 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 5/3/2022 Approved KEVIN SARGSYAN
HVAC-Final 5/3/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 5/3/2022 Approved KEVIN SARGSYAN