5219-5219 1/2 W PACKARD ST 90019

Certificate Information: 5219-5219 1/2 W PACKARD ST 90019

Application / Permit
20016-10000-33394
Plan Check / Job No.
B20LA24120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PORTION OF GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(B)(5) WITHIN DUPLEX
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 1/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 12/29/2020 JOE VO
Corrections Issued 12/29/2020 JOE VO
Applicant returned to address corrections 3/9/2021 CARLOS MONTES
Plan Check Approved 3/30/2021 MONICA RAMIREZ
Issued 6/2/2021 APPLICANT
CofO in Progress 12/6/2021 JOSE AVILA
CofO in Progress 12/13/2021 JOSE AVILA
CofO in Progress 12/21/2021 JOSE AVILA
Permit Finaled 1/14/2022 DEROLD HAUFF
CofO Issued 1/14/2022 DEROLD HAUFF
Permit Finaled 1/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/16/2021 JEANIE LAM
Sewer availability Cleared 2/16/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/10/2021 JEANIE LAM

Contact Information

Contractor Tsfira Zohar; Lic. No.: 860984-B 8222 MELROSE AVENUE   # 207    LOS ANGELES, CA 90046
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/28/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 8/2/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 8/2/2021 Partial Approval KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 8/5/2021 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 9/2/2021 Approved FREDDIE RIVERA
Gas Test 9/2/2021 Approved FREDDIE RIVERA
HVAC-Rough 9/2/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/2/2021 Approved FREDDIE RIVERA
Wood Frame 9/2/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 9/9/2021 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 9/14/2021 Not Ready for Inspection CALEB MEISTER
Wood Frame 9/17/2021 Approved ALFREDO BALANDRA
Insulation 9/23/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 9/23/2021 Approved WILLIAM WREN
Drywall Nailing 9/27/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 10/5/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/8/2021 Approved JOSE AVILA
ELECTRICAL-Final 11/8/2021 Approved JOSE AVILA
Final 11/8/2021 Order to Comply Issued JOSE AVILA
Green Building Final 11/8/2021 Order to Comply Issued JOSE AVILA
Green Building Rough 11/8/2021 Approved JOSE AVILA
HVAC-Final 11/8/2021 Corrections Issued JOSE AVILA
METHANE-Final 11/8/2021 Approved JOSE AVILA
METHANE-Rough 11/8/2021 Approved JOSE AVILA
PLUMBING-Final 11/8/2021 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Approved JOSE AVILA
Smoke Detectors 11/8/2021 Approved JOSE AVILA
HVAC-Final 11/18/2021 Corrections Issued JOSE AVILA
PLUMBING-Final 11/18/2021 Approved JOSE AVILA
Service/Power Release 11/18/2021 Approved JOSE AVILA
HVAC-Final 11/24/2021 Approved JOSE AVILA
Final 12/3/2021 OK to Issue CofO JOSE AVILA
Green Building Final 12/3/2021 Approved JOSE AVILA