3518 S REDONDO BLVD 90016

Certificate Information: 3518 S REDONDO BLVD 90016

Application / Permit
20016-10000-33379
Plan Check / Job No.
B20LA24100
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of an (E) detached 2-car garage into an ADU per State Law 65852.2(e)(1)(A). All works per Wood Frame Prescription Provisions.
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2021 APPLICANT
Assigned to Plan Check Engineer 1/5/2021 HELEN NGUYEN
Corrections Issued 1/5/2021 HELEN NGUYEN
Applicant returned to address corrections 4/6/2021 HELEN NGUYEN
Applicant returned to address corrections 4/15/2021 HELEN NGUYEN
Plan Check Approved 4/20/2021 HELEN NGUYEN
Issued 4/29/2021 APPLICANT
CofO in Progress 11/22/2021 JOSE AVILA
Permit Finaled 12/3/2021 DEROLD HAUFF
CofO Issued 12/3/2021 DEROLD HAUFF
Permit Finaled 12/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/17/2021 ROSA SILVA
Sewer availability Cleared 3/17/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/23/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2021 Not Ready for Inspection DAVID FEILER
Pre-Inspection 5/13/2021 Partial Inspection DAVID FEILER
Deputy Drilled-In Anchors 6/18/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 6/23/2021 Approved RICHARD STEINBACH
ELECTRICAL-Rough 7/8/2021 Approved STUART CHAPMAN
PLUMBING-Rough 7/8/2021 Partial Approval STUART CHAPMAN
Sewer 7/8/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 7/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 7/22/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Approved JUSTIN HAWLEY
Gas Test 7/29/2021 Approved JUSTIN HAWLEY
Insulation 7/29/2021 Approved JUSTIN HAWLEY
Drywall Nailing 8/3/2021 Approved JESUS PINEDA
Green Building Rough 8/3/2021 Approved JESUS PINEDA
Shower Pan 8/5/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 9/23/2021 Approved DAVID FEILER
Final 9/23/2021 Corrections Issued DAVID FEILER
Green Building Final 9/23/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 9/23/2021 Not Ready for Inspection DAVID FEILER
Final 10/18/2021 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 10/18/2021 Approved LILIANA PORTILLO
Final 10/26/2021 Conditional Approval JOSE AVILA
Gas Test 11/2/2021 Approved JOSE AVILA
Service/Power Release 11/2/2021 Approved JOSE AVILA
ELECTRICAL-Final 11/3/2021 Approved JOSE AVILA
HVAC-Final 11/3/2021 Approved JOSE AVILA
PLUMBING-Final 11/3/2021 Approved JOSE AVILA
Final 11/19/2021 OK to Issue CofO JOSE AVILA