930 N LINDA FLORA DR 90049

Certificate Information: 930 N LINDA FLORA DR 90049

Application / Permit
20016-10000-33353
Plan Check / Job No.
B20LA24048
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR ALTERATIONS TO AN EXISTING SINGLE FAMILY DWELLING. CONVERT UTILITY ROOM TO WALK-IN CLOSET. KITCHEN REMODEL. NEW WINDOWS AT KITCHEN, WALKIN CLOSET AND MASTER BEDROOM. ENCLOSE EXISTING PATIO.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 MANUEL MONTUFAR
Corrections Issued 2/22/2021 MANUEL MONTUFAR
Quality Review Completed 2/24/2021 EUGENE BARBEAU
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 4/15/2021 MANUEL MONTUFAR
Plan Check Approved 4/21/2021 MANUEL MONTUFAR
Issued 4/21/2021 APPLICANT
CofO in Progress 9/13/2024 CARLOS MATAMOROS
Permit Finaled 9/16/2024 RICHARD STEINBACH
CofO Issued 9/16/2024 RICHARD STEINBACH
Permit Finaled 9/16/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/5/2021 KIRK LINKLATER

Contact Information

Contractor G S Tingling; Lic. No.: 952884-B 7725 GATEWAY   UNIT 2253    IRVINE, CA 92618
Engineer Gonzalez,, Fernando Francisco; Lic. No.: C53256 11607 AMESTOY AVE      GRANADA HILLS, CA 91344

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 6/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 6/28/2021 Corrections Issued CARLOS MATAMOROS
Deputy Drilled-In Anchors 7/7/2021 Conditional Approval CARLOS MATAMOROS
Deputy Wood Construction 7/12/2021 Approved CARLOS MATAMOROS
Green Building Rough 7/12/2021 Approved CARLOS MATAMOROS
Insulation 7/12/2021 Approved CARLOS MATAMOROS
Wood Frame 7/12/2021 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 9/30/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 11/19/2021 Partial Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 7/6/2022 Conditional Approval CARLOS MATAMOROS
Wood Frame 7/20/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved CARLOS MATAMOROS
Insulation 4/28/2023 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 4/28/2023 Not Ready for Inspection CARLOS MATAMOROS
Insulation 5/2/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/2/2023 Approved CARLOS MATAMOROS
Drywall Nailing 6/1/2023 Approved CHRISTOPHER WILSON
Final 5/23/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 5/23/2024 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 5/23/2024 Partial Approval CARLOS MATAMOROS
Final 6/21/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 6/21/2024 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 6/21/2024 Approved CARLOS MATAMOROS
Final 9/6/2024 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/6/2024 Approved CARLOS MATAMOROS