700 W 7TH ST S260A 90017
Certificate Information: 700 W 7TH ST S260A 90017
- Application / Permit
- 20016-10000-33167
- Plan Check / Job No.
- B20LA23902
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TI TO (E) STREEL LEVEL RETAIL TENANT. NEW TENANT DEMISING WALL
- Permit Issued
- Issued on 7/23/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/30/2022
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2021 | TSE MING HUANG |
| Corrections Issued | 2/17/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 6/28/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 6/28/2021 | FARSHAD ALIMOHAMADI |
| Issued | 7/23/2021 | APPLICANT |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Permit Finaled | 1/7/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 6/7/2021 | ANDREW KO |
Contact Information
| Contractor | Swinerton Builders; Lic. No.: 92-B | 2001 CLAYTON RD 7TH FLOOR LEGAL CONCORD, CA 94520 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 8/25/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Insulation | 8/25/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 8/25/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 8/27/2021 | Partial Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 8/27/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 9/1/2021 | Partial Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Partial Approval | DANIEL COLLINS |
| Insulation | 9/24/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 9/27/2021 | Approved | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 9/27/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 9/27/2021 | Approved | TIMOTHY BUXTON |
| Final | 1/7/2022 | Permit Finaled | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 1/7/2022 | Approved | TIMOTHY BUXTON |