3677 S 2ND AVE 90018

Certificate Information: 3677 S 2ND AVE 90018

Application / Permit
20016-10000-33088
Plan Check / Job No.
B20LA23804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Attn: Monica 01.27.2021 Convert existing permitted detached recreational room to a detached accessory dwelling unit per LAMC 12.22 A.33 (b)(5)
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 10/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 JOE VO
Corrections Issued 12/23/2020 JOE VO
Applicant returned to address corrections 1/20/2021 MONICA RAMIREZ
Applicant returned to address corrections 1/27/2021 MONICA RAMIREZ
Plan Check Approved 2/18/2021 MONICA RAMIREZ
Issued 2/19/2021 APPLICANT
CofO in Progress 9/20/2021 STUART CHAPMAN
Permit Finaled 10/4/2021 DEROLD HAUFF
CofO Issued 10/4/2021 DEROLD HAUFF
Permit Finaled 10/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/4/2021 RIDWAN HARDY
Address approval Cleared 1/13/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 RENZ SORIANO
Sewer availability Cleared 1/13/2021 RENZ SORIANO
CPC Cleared 1/25/2021 MAX LODER
HPOZ Cleared 1/25/2021 MAX LODER
Historic monument Cleared 1/25/2021 MAX LODER
Hydrant and Access approval Cleared 2/5/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2021 Approved STUART CHAPMAN
Pre-Inspection 3/8/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 6/30/2021 Not Ready for Inspection DAVID FEILER
Final 7/19/2021 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/4/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 8/19/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 8/19/2021 Approved STUART CHAPMAN
Final 8/19/2021 Conditional Approval STUART CHAPMAN
HVAC-Final 8/19/2021 Approved STUART CHAPMAN
PLUMBING-Final 8/19/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/19/2021 Approved STUART CHAPMAN
Final 9/17/2021 OK to Issue CofO STUART CHAPMAN