218-220 W 40TH PL 90037
Certificate Information: 218-220 W 40TH PL 90037
- Application / Permit
- 20016-10000-33045
- Plan Check / Job No.
- B20LA23735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE BELOW (E) SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Current Status
- Issued on 5/19/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | KEVIN MORALES |
| Corrections Issued | 3/10/2021 | KEVIN MORALES |
| Plan Check Approved | 5/19/2021 | KEVIN MORALES |
| Issued | 5/19/2021 | APPLICANT |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/29/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 5/11/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Lord'S Construction; Lic. No.: 854236-B | 15364 NARANJA AVERNUE PARAMOUNT, CA 90723 |
| Engineer | Hazrati,, Kayvan Naghib; Lic. No.: C60556 | 465 PUERTO DEL MAR PACIFIC PALISADES, CA 90272 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/23/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/10/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/13/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 9/13/2021 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/13/2021 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 9/13/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/21/2021 | Approved | HORACE FULTZ |
| HVAC-Rough | 10/21/2021 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 10/21/2021 | Approved | HORACE FULTZ |
| Wood Frame | 10/21/2021 | Approved | HORACE FULTZ |
| Insulation | 10/26/2021 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 11/16/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 1/31/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 1/31/2022 | Approved | JOAQUIN GREENOUGH |