218-220 W 40TH PL 90037

Certificate Information: 218-220 W 40TH PL 90037

Application / Permit
20016-10000-33045
Plan Check / Job No.
B20LA23735
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE BELOW (E) SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
Issued on 5/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 KEVIN MORALES
Corrections Issued 3/10/2021 KEVIN MORALES
Plan Check Approved 5/19/2021 KEVIN MORALES
Issued 5/19/2021 APPLICANT
Building Plans Picked Up 5/20/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2021 CECILIO NAVARRO
Sewer availability Cleared 4/29/2021 CECILIO NAVARRO
Address approval Cleared 5/11/2021 CECILIO NAVARRO

Contact Information

Contractor Lord'S Construction; Lic. No.: 854236-B 15364 NARANJA AVERNUE      PARAMOUNT, CA 90723
Engineer Hazrati,, Kayvan Naghib; Lic. No.: C60556 465 PUERTO DEL MAR      PACIFIC PALISADES, CA 90272

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2021 Conditional Approval JOAQUIN GREENOUGH
Underground Mechanical 6/16/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/23/2021 No Access for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/29/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/10/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/13/2021 Approved WILLIAM WREN
ELECTRICAL-Rough 9/13/2021 Approved WILLIAM WREN
HVAC-Rough 9/13/2021 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 9/13/2021 Approved WILLIAM WREN
ELECTRICAL-Rough 9/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/23/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 9/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 9/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/21/2021 Approved HORACE FULTZ
HVAC-Rough 10/21/2021 Approved HORACE FULTZ
PLUMBING-Rough 10/21/2021 Approved HORACE FULTZ
Wood Frame 10/21/2021 Approved HORACE FULTZ
Insulation 10/26/2021 Corrections Issued JUSTIN HAWLEY
Insulation 11/2/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 11/16/2021 Approved JOAQUIN GREENOUGH
Final 1/31/2022 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 1/31/2022 Approved JOAQUIN GREENOUGH