14957 W SYLVAN ST 91411
Certificate Information: 14957 W SYLVAN ST 91411
- Application / Permit
- 20016-10000-32826
- Plan Check / Job No.
- B20LA23587
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. GROUND FLOOR ADDITION TO GARAGE AND CONVERT TO ADU PER ORDINANCE.
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | JOE VO |
| Corrections Issued | 12/22/2020 | JOE VO |
| Applicant returned to address corrections | 1/25/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/27/2021 | HELEN NGUYEN |
| Plan Check Approved | 2/4/2021 | MONICA RAMIREZ |
| Issued | 2/10/2021 | APPLICANT |
| CofO in Progress | 10/14/2021 | RICHARD DOCKUS |
| Permit Finaled | 11/24/2021 | MICHAEL SMITH |
| CofO Issued | 11/24/2021 | MICHAEL SMITH |
| Permit Finaled | 11/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/25/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/25/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2021 | Approved | JOHN HAYES |
| Sewer | 3/12/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/19/2021 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 5/19/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 6/4/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 6/4/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 7/21/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/22/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 7/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 7/22/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/28/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/28/2021 | Approved | JOHN HAYES |
| Green Building Rough | 7/28/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 7/28/2021 | Approved | JOHN HAYES |
| PLUMBING-Rough | 7/28/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 10/1/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 10/1/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 10/1/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 10/1/2021 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/1/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 10/1/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 10/1/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/7/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 10/7/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/12/2021 | Approved | RICHARD DOCKUS |
| Final | 10/12/2021 | OK to Issue CofO | RICHARD DOCKUS |