14957 W SYLVAN ST 91411

Certificate Information: 14957 W SYLVAN ST 91411

Application / Permit
20016-10000-32826
Plan Check / Job No.
B20LA23587
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. GROUND FLOOR ADDITION TO GARAGE AND CONVERT TO ADU PER ORDINANCE.
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/22/2020 JOE VO
Corrections Issued 12/22/2020 JOE VO
Applicant returned to address corrections 1/25/2021 MONICA RAMIREZ
Applicant returned to address corrections 1/27/2021 HELEN NGUYEN
Plan Check Approved 2/4/2021 MONICA RAMIREZ
Issued 2/10/2021 APPLICANT
CofO in Progress 10/14/2021 RICHARD DOCKUS
Permit Finaled 11/24/2021 MICHAEL SMITH
CofO Issued 11/24/2021 MICHAEL SMITH
Permit Finaled 11/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/25/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/25/2021 LEE GUILBEAUX
Sewer availability Cleared 1/25/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/25/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/27/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2021 Approved JOHN HAYES
Sewer 3/12/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/31/2021 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/19/2021 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 5/19/2021 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/4/2021 Corrections Issued MATTHEW NELSON
Green Building Rough 6/4/2021 Not Ready for Inspection MATTHEW NELSON
Deputy Drilled-In Anchors 7/21/2021 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 7/22/2021 Partial Approval MARK JOHNSON
Green Building Rough 7/22/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 7/22/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 7/22/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 7/28/2021 Approved JOHN HAYES
ELECTRICAL-Rough 7/28/2021 Approved JOHN HAYES
Green Building Rough 7/28/2021 Approved JOHN HAYES
HVAC-Rough 7/28/2021 Approved JOHN HAYES
PLUMBING-Rough 7/28/2021 Approved JOHN HAYES
Drywall Nailing 8/9/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 8/9/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 10/1/2021 Corrections Issued RICHARD DOCKUS
Final 10/1/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 10/1/2021 Approved RICHARD DOCKUS
Green Building Final 10/1/2021 Approved RICHARD DOCKUS
HVAC-Final 10/1/2021 Approved RICHARD DOCKUS
PLUMBING-Final 10/1/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 10/1/2021 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/7/2021 Not Ready for Inspection RICHARD DOCKUS
Final 10/7/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 10/12/2021 Approved RICHARD DOCKUS
Final 10/12/2021 OK to Issue CofO RICHARD DOCKUS