5432 W WESTHAVEN ST 90016

Certificate Information: 5432 W WESTHAVEN ST 90016

Application / Permit
20016-10000-32815
Plan Check / Job No.
B20LA23580
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/28/2020 FARSHAD ALIMOHAMADI
Corrections Issued 12/29/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/9/2021 GEORGE ALVAREZ
Applicant returned to address corrections 3/26/2021 SAMUEL GONZALEZ
Plan Check Approved 4/7/2021 ADAM HEGAZI
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/20/2021 APPLICANT
CofO in Progress 2/3/2022 JOSE AVILA
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2021 CECILIO NAVARRO
Sewer availability Cleared 1/12/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/15/2021 CECILIO NAVARRO
Construction near power lines Cleared 3/15/2021 RIDWAN HARDY

Contact Information

Contractor Norcio Construction Inc; Lic. No.: 1006731-B 241 5TH AVE      VENICE, CA 90291
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2021 Approved STUART CHAPMAN
Sewer 9/27/2021 Not Ready for Inspection STUART CHAPMAN
Sewer 9/29/2021 Approved CALEB MEISTER
Deputy Reinf. Concrete 10/4/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 10/4/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/7/2021 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 10/18/2021 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 10/18/2021 Approved LILIANA PORTILLO
HVAC-Rough 10/18/2021 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 10/18/2021 Approved LILIANA PORTILLO
Underground Mechanical 10/18/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/9/2021 Approved JOSE AVILA
Green Building Rough 11/9/2021 Approved JOSE AVILA
HVAC-Rough 11/9/2021 Corrections Issued JOSE AVILA
MERV13>=Rough 11/9/2021 Approved JOSE AVILA
HVAC-Rough 11/17/2021 Corrections Issued ADAM ESCOTO
Insulation 11/17/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 11/17/2021 Approved ADAM ESCOTO
Drywall Nailing 11/22/2021 Approved JOSE AVILA
HVAC-Rough 11/22/2021 Approved JOSE AVILA
ELECTRICAL-Final 1/21/2022 Approved JOSE AVILA
HVAC-Final 1/21/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 1/21/2022 Corrections Issued JOSE AVILA
Service/Power Release 1/21/2022 Approved JOSE AVILA
Smoke Detectors 1/21/2022 Approved JOSE AVILA
Final 1/24/2022 Corrections Issued JOSE AVILA
Green Building Final 1/24/2022 Approved JOSE AVILA
MERV13>=Final 1/24/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Approved JOSE AVILA
Final 2/1/2022 OK to Issue CofO JOSE AVILA