5432 W WESTHAVEN ST 90016
Certificate Information: 5432 W WESTHAVEN ST 90016
- Application / Permit
- 20016-10000-32815
- Plan Check / Job No.
- B20LA23580
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/29/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/9/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 3/26/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 4/7/2021 | ADAM HEGAZI |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 2/3/2022 | JOSE AVILA |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/12/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 3/15/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Norcio Construction Inc; Lic. No.: 1006731-B | 241 5TH AVE VENICE, CA 90291 |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2021 | Approved | STUART CHAPMAN |
| Sewer | 9/27/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 9/29/2021 | Approved | CALEB MEISTER |
| Deputy Reinf. Concrete | 10/4/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/4/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/7/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/18/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/18/2021 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/18/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 10/18/2021 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/18/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | JOSE AVILA |
| Green Building Rough | 11/9/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 11/9/2021 | Corrections Issued | JOSE AVILA |
| MERV13>=Rough | 11/9/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 11/17/2021 | Corrections Issued | ADAM ESCOTO |
| Insulation | 11/17/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 11/17/2021 | Approved | ADAM ESCOTO |
| Drywall Nailing | 11/22/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 11/22/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 1/21/2022 | Approved | JOSE AVILA |
| HVAC-Final | 1/21/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 1/21/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 1/21/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 1/21/2022 | Approved | JOSE AVILA |
| Final | 1/24/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/24/2022 | Approved | JOSE AVILA |
| MERV13>=Final | 1/24/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Approved | JOSE AVILA |
| Final | 2/1/2022 | OK to Issue CofO | JOSE AVILA |