11935 W LOUISE AVE 90066

Certificate Information: 11935 W LOUISE AVE 90066

Application / Permit
20016-10000-32803
Plan Check / Job No.
B20LA23571
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE AND ADDITION TO CREATE AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 10/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/29/2020 STANLEY RAAP
Corrections Issued 1/4/2021 STANLEY RAAP
Applicant returned to address corrections 2/10/2021 JESSE JIMENEZ
Applicant returned to address corrections 3/1/2021 FERNANDO FLORES
Applicant returned to address corrections 5/19/2021 JESSE JIMENEZ
Applicant returned to address corrections 6/29/2021 SINA KHOSRAVI
Building Plans Picked Up 7/2/2021 APPLICANT
Plan Check Approved 10/16/2021 FERNANDO FLORES
Issued 3/2/2022 APPLICANT
CofO in Progress 10/15/2022 JESUS RODRIGUEZ
Permit Finaled 10/24/2022 DANIEL ORRANTE
CofO Issued 10/24/2022 DANIEL ORRANTE
Permit Finaled 10/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 2/26/2021 MARTIN FRAGOSO
Address approval Cleared 3/2/2021 DINAH GARIN
Hydrant and Access approval Cleared 3/17/2021 JOHN CONNEALLY
Construction near power lines Cleared 3/20/2021 RIDWAN HARDY
Specific Plan Cleared 3/22/2021 KEVIN ARUCAN
Certificate of Compliance Cleared 4/6/2021 MAXFIELD VERMY
Permit Cleared 6/22/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 6/22/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 6/23/2021 DINAH GARIN
Sewer availability Cleared 6/23/2021 DINAH GARIN

Contact Information

Contractor California Green Home Solutions; Lic. No.: 1043877-B 7020 HAYVENHURST AVE STE B      VAN NUYS, CA 91406
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/23/2022 No Access for Inspection PATRICK QUALEY
Footing/Foundation/Slab 3/25/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 3/25/2022 Partial Approval JOHNNY MIRANDA
Sewer 3/25/2022 Not Ready for Inspection JOHNNY MIRANDA
Pre-Inspection 3/31/2022 Corrections Issued PATRICK QUALEY
Special/Order Compliance 3/31/2022 Partial Inspection MICHAEL PELHAM
Underground Mechanical 4/11/2022 Partial Approval PATRICK QUALEY
BUILDING-Rough-Frame 5/2/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 5/2/2022 Corrections Issued PATRICK QUALEY
BUILDING-Rough-Frame 5/18/2022 Partial Approval PATRICK QUALEY
ELECTRICAL-Rough 5/18/2022 Corrections Issued PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Partial Approval PATRICK QUALEY
Gas Test 5/18/2022 Partial Approval PATRICK QUALEY
Green Building Rough 5/18/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Rough 5/18/2022 Corrections Issued PATRICK QUALEY
Insulation 5/18/2022 Partial Approval PATRICK QUALEY
PLUMBING-Rough 5/18/2022 Corrections Issued PATRICK QUALEY
Underground Mechanical 5/18/2022 Approved PATRICK QUALEY
ELECTRICAL-Rough 5/27/2022 Conditional Approval CLAYTON GRAHAM
Gas Test 5/27/2022 Corrections Issued CLAYTON GRAHAM
Interior/Exterior Lathing 5/27/2022 Approved CLAYTON GRAHAM
PLUMBING-Rough 5/27/2022 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 5/27/2022 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Conditional Approval PATRICK QUALEY
HVAC-Rough 6/1/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 6/1/2022 Approved PATRICK QUALEY
ELECTRICAL-Rough 6/3/2022 Approved PATRICK QUALEY
Insulation 6/7/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 6/14/2022 Approved PATRICK QUALEY
Drywall Nailing 6/14/2022 Approved PATRICK QUALEY
Green Building Rough 6/14/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 6/14/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 7/19/2022 Not Ready for Inspection PATRICK QUALEY
Final 7/19/2022 Corrections Issued PATRICK QUALEY
Green Building Final 7/19/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 7/19/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Final 7/19/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 7/19/2022 Not Ready for Inspection PATRICK QUALEY
Final 8/1/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/1/2022 Approved JESUS RODRIGUEZ
HVAC-Final 8/1/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/1/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 8/1/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/11/2022 Approved JESUS RODRIGUEZ
Final 8/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 8/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 9/13/2022 Approved JESUS RODRIGUEZ
Final 10/11/2022 Not Ready for Inspection HERBERT GIRON
Final 10/14/2022 OK to Issue CofO JESUS RODRIGUEZ