12777 W JEFFERSON BLVD 90066
Certificate Information: 12777 W JEFFERSON BLVD 90066
- Application / Permit
- 20016-10000-32791
- Plan Check / Job No.
- B20LA23562
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Full Compliance with Division 96. VOLUNTARY SEISMIC RETROFIT OF EXISTING THREE STORY OFFICE BUILDING. RETROFIT WORK INCLUDES NEW CONNECTIONS BETWEEN EXTERIOR TILT-UP CONCRETE WALLS AND DIAPHRAGMS AT EACH FLOOR AND ROOF LEVEL, AND NEW CROSS-TIE CONNECTIONS THROUGHOUT THE DIAPHRAGM AT EACH FLOOR AND ROOF LEVEL. RESTRIPING THE DISABLED PARKING SPACES WITH FIXING THE GRADE SLOPE TO COMPLY WITH THE CURRENT CODE AND NO CHANGES TO THE NUMBER OF EXISTING PARKING SPACES.
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/10/2021
Permit Application Status History
| Submitted | 12/22/2020 | APPLICANT |
| Green Plans Picked Up | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | YOUNG KIM |
| Corrections Issued | 2/3/2021 | YOUNG KIM |
| Quality Review Completed | 2/8/2021 | CHARLES CHANG |
| Building Plans Picked Up | 2/16/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/16/2021 | APPLICANT |
| Applicant returned to address corrections | 3/9/2021 | YOUNG KIM |
| Applicant returned to address corrections | 6/29/2021 | YOUNG KIM |
| Applicant returned to address corrections | 7/1/2021 | YOUNG KIM |
| Plan Check Approved | 7/7/2021 | YOUNG KIM |
| Issued | 7/15/2021 | APPLICANT |
| Permit Finaled | 12/9/2021 | GRANT WOODS |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/10/2021 | YOUNG KIM |
| Green Code | Cleared | 7/7/2021 | AARON COSTA |
Contact Information
| Contractor | 360 Construction Group Inc; Lic. No.: 937854-B | 3301 MIRALOMA AVE, SUITE 189 ANAHEIM, CA 92806 |
| Engineer | O'Connell,, Kevin Daniel; Lic. No.: S4707 | 23201 EVALYN AVE TORRANCE, CA 90505 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wall Anchors | 7/22/2021 | Partial Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/26/2021 | Conditional Approval | GRANT WOODS |
| Wall Anchors | 8/2/2021 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/12/2021 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 8/16/2021 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 8/23/2021 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/23/2021 | Conditional Approval | GRANT WOODS |
| Wood Frame | 10/14/2021 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/22/2021 | Conditional Approval | GRANT WOODS |
| Final | 11/18/2021 | Corrections Issued | GRANT WOODS |
| Green Building Final | 11/18/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 11/18/2021 | Approved | GRANT WOODS |
| Final | 12/9/2021 | Permit Finaled | GRANT WOODS |