5808 W SUNSET BLVD 90028
Certificate Information: 5808 W SUNSET BLVD 90028
- Application / Permit
- 20016-10000-32543
- Plan Check / Job No.
- B20LA23397
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR & EXTERIOR TI & ADD. NEW COMMUNICATING STAIR. @ (E) FIRST & 2ND FLOOR OF NETFLIX OFFICE & ADD. NEW CANOPY.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/12/2022
Permit Application Status History
| Submitted | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | GARO TELMI |
| Corrections Issued | 1/6/2021 | GARO TELMI |
| Quality Review Completed | 1/21/2021 | KEN GILL |
| Applicant returned to address corrections | 2/11/2021 | GARO TELMI |
| Green Plans Picked Up | 4/13/2021 | APPLICANT |
| Applicant returned to address corrections | 4/15/2021 | GARO TELMI |
| Applicant returned to address corrections | 5/3/2021 | GARO TELMI |
| Plan Check Approved | 5/24/2021 | GARO TELMI |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Permit Finaled | 9/9/2022 | JONATHAN QUACH |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 2/10/2021 | MICAELA TORRES-GIL |
| Historic Resource Verification | Cleared | 2/10/2021 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 2/10/2021 | MICAELA TORRES-GIL |
| CPC | Cleared | 2/16/2021 | KENTON TRINH |
| CPC | Cleared | 2/16/2021 | KENTON TRINH |
| Redevelopment Project Area | Cleared | 2/23/2021 | DAVID URITA |
| ZI | Cleared | 2/23/2021 | DAVID URITA |
| Green Code | Cleared | 4/9/2021 | AARON COSTA |
| DAS Clearance | Cleared | 4/26/2021 | GARO TELMI |
| Fire Marshal Fire Life Safety | Cleared | 4/26/2021 | OSCAR SALGADO JR |
Contact Information
| Architect | Bieringer,, Lisa A; Lic. No.: C34984 | P O BOX 697 STINSON BEACH, CA 94970 |
| Contractor | Taslimi Construction Co Inc; Lic. No.: 475159-B | 1805 COLORADO AVENUE SANTA MONICA, CA 90404 |
| Engineer | Volnyy,, Vladimir A; Lic. No.: S4817 | 11342 PALA MESA DR NORTHRIDGE, CA 91326 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 6/25/2021 | Approved | JONATHAN QUACH |
| Light Gage Steel Frame | 6/30/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 7/16/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 7/23/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 7/23/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 7/28/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 7/28/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Drywall Nailing | 8/2/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 8/30/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 9/3/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 9/9/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 9/15/2021 | Partial Approval | JONATHAN QUACH |
| Reinforced Masonry Frame | 9/15/2021 | Not Ready for Inspection | JONATHAN QUACH |
| T-Bar Ceiling | 9/15/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Fireproofing | 9/16/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Fireproofing | 9/17/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 9/22/2021 | Conditional Approval | JONATHAN QUACH |
| Drywall Nailing | 9/23/2021 | Partial Inspection | JONATHAN QUACH |
| Final | 9/23/2021 | Partial Inspection | JONATHAN QUACH |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 9/23/2021 | Partial Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 10/1/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 10/1/2021 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/1/2021 | Partial Approval | JONATHAN QUACH |
| Final | 10/4/2021 | Partial Inspection | JONATHAN QUACH |
| Green Building Final | 10/4/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Smoke Detectors | 10/4/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 10/7/2021 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 10/8/2021 | Conditional Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 10/15/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 10/18/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 10/19/2021 | Conditional Approval | SORIN CIRSTOIU |
| Drywall Nailing | 10/25/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 10/25/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 10/26/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 11/3/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 11/16/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 11/19/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 11/19/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Drywall Nailing | 11/22/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 11/22/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 11/24/2021 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 11/29/2021 | Not Ready for Inspection | JONATHAN QUACH |
| T-Bar Ceiling | 12/15/2021 | Approved | JONATHAN QUACH |
| Final | 12/30/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 12/30/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Smoke Detectors | 12/30/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 2/8/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Smoke Detectors | 2/8/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 2/9/2022 | Partial Inspection | JONATHAN QUACH |
| Pre-Inspection | 3/16/2022 | Approved | EDWIN GREGORYONA |
| Final | 9/9/2022 | Permit Finaled | JONATHAN QUACH |
| Green Building Final | 9/9/2022 | Approved | JONATHAN QUACH |
| Smoke Detectors | 9/9/2022 | Approved | JONATHAN QUACH |