2320 3/4 N ALTA ST 90031

Certificate Information: 2320 3/4 N ALTA ST 90031

Application / Permit
20016-10000-32539
Plan Check / Job No.
B20LA23396
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 2 CAR GARAGE TO ADU USING WFPP.
Permit Issued
Issued on 8/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 SAMUEL GONZALEZ
Corrections Issued 12/29/2020 SAMUEL GONZALEZ
Applicant returned to address corrections 3/31/2021 ADAM HEGAZI
Plan Check Approved 4/21/2021 ADAM HEGAZI
Building Plans Picked Up 5/7/2021 APPLICANT
Issued 8/15/2022 APPLICANT
CofO in Progress 7/6/2023 CALEB MEISTER
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/13/2021 RENZ SORIANO
Sewer availability Cleared 1/13/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/14/2021 RENZ SORIANO
Hydrant and Access approval Cleared 3/22/2021 MATTHEW CRAIG

Contact Information

Contractor Minchez Construction Inc; Lic. No.: 1022183-B 11211 OSBORNE STREET      LAKE VIEW TERRACE, CA 91342

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/4/2023 Approved GORDON ZUBER
Excavation/Setback/Form/Re-Bar 2/11/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/11/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/1/2023 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/1/2023 Approved CALEB MEISTER
HVAC-Rough 4/1/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 4/1/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 4/15/2023 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 4/15/2023 Approved CALEB MEISTER
HVAC-Rough 4/15/2023 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 4/15/2023 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 4/22/2023 Approved AMY COLIN
ELECTRICAL-Rough 4/22/2023 Approved AMY COLIN
HVAC-Rough 4/22/2023 Approved AMY COLIN
Underground Mechanical 4/22/2023 Approved AMY COLIN
Insulation 4/29/2023 Approved RICHARD ROBLES
Underground Mechanical 4/29/2023 Partial Approval RICHARD ROBLES
Drywall Nailing 5/6/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/6/2023 Approved JUAN VALENZUELA
Underground Mechanical 5/6/2023 Partial Approval JUAN VALENZUELA
ELECTRICAL-Final 6/17/2023 Approved MORRIS JACKSON
Final 6/17/2023 Partial Approval MORRIS JACKSON
HVAC-Final 6/17/2023 Approved MORRIS JACKSON
PLUMBING-Final 6/17/2023 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/17/2023 SGSOV Not Required MORRIS JACKSON
Service/Power Release 6/17/2023 Approved MORRIS JACKSON
Smoke Detectors 6/17/2023 Approved MORRIS JACKSON
Final 7/6/2023 OK to Issue CofO CALEB MEISTER