4926 S 3RD AVE 90043

Certificate Information: 4926 S 3RD AVE 90043

Application / Permit
20016-10000-32537
Plan Check / Job No.
B20LA23392
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION EXISTING DETACHED GARAGE TO ACCESSORY DEWLLING UNIT PER ENGINEER DESIGN (CONVERSION OF ACCESSORY BUILDING PER STATE LAW).
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/28/2020 AUNG SOE
Corrections Issued 1/5/2021 AUNG SOE
Building Plans Picked Up 1/7/2021 APPLICANT
Plan Check Approved 2/9/2021 GEORGE ALVAREZ
Issued 3/16/2021 APPLICANT
CofO in Progress 1/25/2022 ANTHONY EGSON
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/14/2021 RENZ SORIANO
Sewer availability Cleared 1/14/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/19/2021 RENZ SORIANO

Contact Information

Contractor Norcio Construction Inc; Lic. No.: 1006731-B 241 5TH AVE      VENICE, CA 90291
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/22/2021 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 3/22/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 3/22/2021 Partial Approval DAVID FEILER
Pre-Inspection 3/22/2021 Not Ready for Inspection DAVID FEILER
Sewer 3/22/2021 Approved DAVID FEILER
Footing/Foundation/Slab 3/31/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 3/31/2021 Partial Approval DAVID FEILER
Footing/Foundation/Slab 4/7/2021 Approved FREDDIE RIVERA
Green Building Rough 4/7/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 4/7/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 4/15/2021 Approved DAVID FEILER
HVAC-Rough 4/15/2021 Approved DAVID FEILER
Wood Frame 4/15/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 4/19/2021 Partial Approval DAVID FEILER
Green Building Rough 4/19/2021 Approved DAVID FEILER
Interior/Exterior Lathing 4/19/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 4/19/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 4/26/2021 Approved SABAS ALONSO
Insulation 4/26/2021 Approved SABAS ALONSO
Drywall Nailing 4/30/2021 Approved CHRISTOPHER DELLEFIELD
Gas Test 8/19/2021 Order to Comply Issued FREDDIE RIVERA
ELECTRICAL-Final 9/15/2021 Not Ready for Inspection DAVID FEILER
Final 9/15/2021 Corrections Issued DAVID FEILER
Green Building Final 9/15/2021 Not Ready for Inspection DAVID FEILER
HVAC-Final 9/15/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 9/15/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready DAVID FEILER
Service/Power Release 9/15/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 9/15/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 10/8/2021 Partial Inspection DAVID FEILER
Final 10/8/2021 Partial Inspection DAVID FEILER
Green Building Final 10/8/2021 Approved DAVID FEILER
HVAC-Final 10/8/2021 Approved DAVID FEILER
PLUMBING-Final 10/8/2021 Partial Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 10/8/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 11/5/2021 Corrections Issued ANTHONY EGSON
Final 11/5/2021 Corrections Issued ANTHONY EGSON
Service/Power Release 11/5/2021 Corrections Issued ANTHONY EGSON
Smoke Detectors 11/5/2021 Approved ANTHONY EGSON
Special/Order Compliance 11/5/2021 Partial Inspection JUSTIN HAWLEY
ELECTRICAL-Final 11/16/2021 Approved ANTHONY EGSON
Final 11/16/2021 OK to Issue CofO ANTHONY EGSON
Grounding or Bonding 11/16/2021 Approved ANTHONY EGSON
HVAC-Final 11/16/2021 Approved ANTHONY EGSON
Service/Power Release 11/16/2021 Approved ANTHONY EGSON