1815 N PARK DR 90026
Certificate Information: 1815 N PARK DR 90026
- Application / Permit
- 20016-10000-32430
- Plan Check / Job No.
- B20LA23313
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & ALTERATION TO (E) SINGLE FAMILY DWELLING & CONVERT (E) 248 S.F. OF UNDER FLOOR AREA TO HABITABLE ARAE & ADD UNCOVERED ATTACHED DEACK & STAIRS TO REAR OF BUILDING.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | GARO TELMI |
| Corrections Issued | 12/30/2020 | GARO TELMI |
| Quality Review Completed | 1/11/2021 | WING SUEN |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Applicant returned to address corrections | 2/25/2021 | GARO TELMI |
| Applicant returned to address corrections | 3/25/2021 | GARO TELMI |
| Plan Check Approved | 5/5/2021 | GARO TELMI |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | THOMAS LOGRASSO |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
| CofO Issued | 1/21/2023 | DEROLD HAUFF |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/3/2021 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 1/25/2021 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/8/2021 | RENZ SORIANO |
| Street Frontage | Cleared | 2/8/2021 | RENZ SORIANO |
Contact Information
| Architect | Cooke,, Barrett H; Lic. No.: C37365 | 5239 WINDERMERE AVE LOS ANGELES, CA 90041 |
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/15/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 7/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/3/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/5/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/15/2021 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/1/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 3/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/15/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/13/2022 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 5/24/2022 | Corrections Issued | THOMAS LOGRASSO |
| Shower Pan | 5/31/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 11/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 11/30/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 12/7/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/12/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | THOMAS LOGRASSO |