1417 S FAIRFAX AVE 90019
Certificate Information: 1417 S FAIRFAX AVE 90019
- Application / Permit
- 20016-10000-32423
- Plan Check / Job No.
- B20LA23301
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING BACK TO BACK HARDY FRAME STRONG WALLS W/ GRADE BEAM.
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofC Issued on 4/13/2022
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | HANS SANTIAGO |
| Corrections Issued | 1/11/2021 | HANS SANTIAGO |
| Quality Review Completed | 1/15/2021 | DAVID CHANG |
| Applicant returned to address corrections | 2/5/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/27/2021 | ANDREW SANTIAGO |
| Issued | 11/5/2021 | APPLICANT |
| OK for CofC | 4/12/2022 | DARRYL ARNOLD |
| CofC Issued | 4/13/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/20/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2021 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 1/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 1/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 2/9/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 2/9/2022 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/3/2022 | Approved | DARRYL ARNOLD |
| Final | 3/14/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/14/2022 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 3/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/12/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 4/12/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/12/2022 | Approved | DARRYL ARNOLD |