1863 W 37TH PL 90018

Certificate Information: 1863 W 37TH PL 90018

Application / Permit
20016-10000-32395
Plan Check / Job No.
B20LA23275
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERSION OF A GARAGE INTO AN ADU WITH THE ADDITION OF 93 sf.
Permit Issued
Issued on 6/6/2021
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 LARRY LEE
Corrections Issued 12/17/2020 LARRY LEE
Applicant returned to address corrections 12/23/2020 JOE VO
Applicant returned to address corrections 12/29/2020 MONICA RAMIREZ
Applicant returned to address corrections 1/20/2021 MONICA RAMIREZ
Applicant returned to address corrections 2/2/2021 MONICA RAMIREZ
Applicant returned to address corrections 3/2/2021 LARRY LEE
Plan Check Approved 3/29/2021 LARRY LEE
Issued 6/6/2021 APPLICANT
CofO in Progress 11/12/2024 SABAS ALONSO
CofO Issued 11/13/2024 DEROLD HAUFF
Permit Finaled 11/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/11/2021 JEANIE LAM
Sewer availability Cleared 1/11/2021 JEANIE LAM

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: NA38075       ,
Contractor Melt Construction Inc; Lic. No.: 996599-B 1411 TOWER GROVE DRIVE      BEVERLY HILLS, CA 90210

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 6/17/2021 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Wall Anchors 6/17/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/24/2021 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 6/30/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved SABAS ALONSO
Green Building Rough 8/13/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved SABAS ALONSO
Wall Anchors 8/13/2021 Not Ready for Inspection SABAS ALONSO
Wood Frame 8/13/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 8/18/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 8/18/2021 Approved SABAS ALONSO
Insulation 8/20/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 8/20/2021 Approved SABAS ALONSO
Drywall Nailing 8/27/2021 Approved SABAS ALONSO
Pre-Inspection 8/27/2021 Partial Inspection JESUS PINEDA
Insulation 9/10/2021 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 9/14/2021 Approved SABAS ALONSO
Final 11/8/2024 OK to Issue CofO SABAS ALONSO
Green Building Final 11/8/2024 Approved SABAS ALONSO
Smoke Detectors 11/8/2024 Approved SABAS ALONSO
Wood Frame 11/8/2024 Approved SABAS ALONSO