3450 S WATT WAY 90089
Certificate Information: 3450 S WATT WAY 90089
- Application / Permit
- 20016-10000-32350
- Plan Check / Job No.
- B20LA23247
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School - private
- Work Description
- STRUCTURAL ALTERATION TO THE EXISTING 3 STORY BUILDING
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/8/2021
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2020 | LARRY LEE |
| Corrections Issued | 1/6/2021 | LARRY LEE |
| Quality Review Completed | 1/6/2021 | CHARLES CHANG |
| Applicant returned to address corrections | 2/1/2021 | LARRY LEE |
| Applicant returned to address corrections | 3/4/2021 | LARRY LEE |
| Green Plans Picked Up | 3/23/2021 | APPLICANT |
| Plan Check Approved | 4/27/2021 | LARRY LEE |
| Issued | 4/29/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| Permit Finaled | 11/4/2021 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/21/2021 | ANACANY HURTADO |
| ZI | Cleared | 1/28/2021 | MELISSA JONES |
| Green Code | Cleared | 3/23/2021 | LARRY LEE |
| DAS Clearance | Cleared | 3/31/2021 | SHINE LIN |
Contact Information
| Architect | Hamner,, Derek Michael; Lic. No.: C19023 | 1131 KENTON DRIVE MONTEREY PARK, CA 91755 |
| Contractor | Hamilton Healthcare Construction Inc; Lic. No.: 698100-B | 202 MERCURY CIRCLE POMONA, CA 91768 |
| Engineer | Varela,, Gregorio; Lic. No.: C81201 | 1108 S ADAMS ST GLENDALE, CA 91205 |
| Engineer | Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 5/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 5/24/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 6/3/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 6/7/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/7/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 6/7/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/7/2021 | Partial Approval | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 6/7/2021 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 6/9/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 6/10/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Shotcrete | 6/10/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/11/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 6/14/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Shotcrete | 6/15/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 6/15/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Shotcrete | 6/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 6/17/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Shotcrete | 6/17/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 6/18/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Shotcrete | 6/18/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2021 | Partial Approval | KATY RAMIREZ |
| Deputy Shotcrete | 6/21/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/22/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/23/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/24/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/25/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/28/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/29/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Structural Steel Frame | 6/29/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/30/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 7/1/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/1/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/1/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/2/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/2/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/6/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/6/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/7/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/7/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/8/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/8/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 7/8/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/9/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/9/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/12/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/12/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 7/13/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/13/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 7/14/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/14/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/14/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/15/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/15/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/19/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/19/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/20/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/20/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 7/22/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/22/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/22/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 7/23/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/23/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/26/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/27/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 7/27/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Insulation | 7/27/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 7/27/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 7/27/2021 | Partial Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 7/27/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/28/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/29/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 7/30/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/2/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 8/2/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/3/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 8/3/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/3/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 8/3/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/4/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/5/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/6/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Insulation | 8/11/2021 | Approved | LEOPOLDO MENDOZA |
| Pre-Inspection | 8/11/2021 | Corrections Issued | LEOPOLDO MENDOZA |
| Green Building Final | 8/19/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 8/19/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 8/20/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 8/20/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 11/4/2021 | Permit Finaled | RUSSELL BONVOULOIR |
| Green Building Final | 11/4/2021 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV No Gas | RUSSELL BONVOULOIR |