738 W 27TH ST #14 90007

Certificate Information: 738 W 27TH ST #14 90007

Application / Permit
20016-10000-32340
Plan Check / Job No.
B20LA23239
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT CARPORT IN EXISTING APARTMENT BUILDING TO ADU PER CA GOVT CODE 65852.2(E)(1)(C)
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/22/2020 AUNG SOE
Corrections Issued 12/28/2020 AUNG SOE
Applicant returned to address corrections 2/9/2021 CRISTINA SALAZAR
Applicant returned to address corrections 3/10/2021 JESSE JIMENEZ
Applicant returned to address corrections 4/7/2021 STARR CHEN
Plan Check Approved 7/14/2021 JOSEPH RAFOLS
Issued 7/15/2021 APPLICANT
Building Plans Picked Up 7/22/2021 APPLICANT
CofO in Progress 7/18/2023 WINSTON DUNNING
CofO Issued 7/18/2023 WINSTON DUNNING
Permit Finaled 7/18/2023 WINSTON DUNNING

Permit Application Clearance Information

Address approval Cleared 1/13/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/14/2021 THOMAS LANG
Sewer availability Cleared 1/19/2021 THOMAS LANG
ZI Cleared 1/20/2021 DANIEL MATA
Redevelopment Project Area Cleared 2/18/2021 GRACIELA ACOSTA
Miscellaneous Cleared 4/23/2021 STARR CHEN
Fire Marshal Fire Life Safety Cleared 6/30/2021 OSCAR SALGADO JR

Contact Information

Architect Bogdan, Vladimirov Tomalevski; Lic. No.: C34688 4310 JASMINE AVENUE      CULVER CITY, CA 90230
Contractor Owner-Builder       ,
Engineer Boranian,, Paul Darian; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2021 Corrections Issued LEOPOLDO MENDOZA
Footing/Foundation/Slab 9/15/2021 Approved LEOPOLDO MENDOZA
Deputy Reinf. Concrete 9/16/2021 Conditional Approval LEOPOLDO MENDOZA
METHANE-Rough 11/16/2021 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 11/16/2021 Partial Inspection RUSSELL BONVOULOIR
METHANE-Rough 2/15/2022 Approved RUSSELL BONVOULOIR
Wood Frame 2/15/2022 Conditional Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 2/23/2022 Approved RUSSELL BONVOULOIR
Insulation 2/28/2022 Approved TIMOTHY BUXTON
Drywall Nailing 3/9/2022 Approved RAFAEL ESPINOZA
Final 5/26/2022 Not Ready for Inspection RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 5/26/2022 Approved RUSSELL BONVOULOIR
Wood Frame 5/26/2022 Approved RUSSELL BONVOULOIR
Final 7/18/2023 Conditional Approval WINSTON DUNNING