1437 S CURSON AVE 90019

Certificate Information: 1437 S CURSON AVE 90019

Application / Permit
20016-10000-32336
Plan Check / Job No.
B20LA23238
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Interior remodel in existing two story duplex to create new bedroom and one bathroom. Existing kitchen and bathroom remodel. Work limited to first floor unit.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
Permit Finaled on 9/16/2021

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/22/2020 AUNG SOE
Corrections Issued 12/28/2020 AUNG SOE
Applicant returned to address corrections 2/26/2021 LUKE GONZALES
Plan Check Approved 3/16/2021 RICARDO RAMIREZ
Issued 4/7/2021 APPLICANT
Building Plans Picked Up 4/9/2021 APPLICANT
Permit Finaled 9/16/2021 STUART CHAPMAN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/14/2021 PHILLIP MUNGUIA
Sewer availability Cleared 1/20/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/22/2021 CECILIO NAVARRO

Contact Information

Contractor Misong Corporation; Lic. No.: 755122-B 936 S ALVARADO STREET      LOS ANGELES, CA 90006
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/20/2021 No Result Entered CHARLENE BUSTAMANTE
Excavation/Setback/Form/Re-Bar 4/20/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/20/2021 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/23/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 4/23/2021 Not Ready for Inspection RUBEN SALAS
Special/Order Compliance 4/23/2021 Corrections Issued RUBEN SALAS
Excavation/Setback/Form/Re-Bar 5/5/2021 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/5/2021 Approved KATHRYN BUTTERWORTH
Special/Order Compliance 6/11/2021 Corrections Issued SCOTT FINNILA
Wood Frame 6/11/2021 Corrections Issued SCOTT FINNILA
Wood Frame 6/18/2021 Corrections Issued STUART CHAPMAN
Insulation 6/25/2021 Approved BENEVA JACKSON
Wood Frame 6/25/2021 Corrections Issued BENEVA JACKSON
Drywall Nailing 7/6/2021 No Access for Inspection CALEB MEISTER
Drywall Nailing 7/12/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 7/30/2021 Approved JUSTIN HAWLEY
Wood Frame 8/11/2021 Approved KATHRYN BUTTERWORTH
Final 8/31/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 8/31/2021 Approved JOAQUIN GREENOUGH
Final 9/3/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Final 9/16/2021 Permit Finaled STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved STUART CHAPMAN