11641 W KLING ST 91602
Certificate Information: 11641 W KLING ST 91602
- Application / Permit
- 20016-10000-32299
- Plan Check / Job No.
- B20LA23203
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GUEST HOUSE TO BE CONVERTED INTO ACCESSORY DWELLING UNIT WITH (E) 124SF COVERED PORCH TO BE ENCLOSED PER GCS 65852.2(e)(1)(A). ALL WORK PER WOOD FRAME PRESCRIPTIVE DESIGN.
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | ZAW HAN |
| Corrections Issued | 12/30/2020 | ZAW HAN |
| Applicant returned to address corrections | 1/20/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 2/8/2021 | FERNANDO FLORES |
| Plan Check Approved | 2/18/2021 | FERNANDO FLORES |
| Issued | 2/18/2021 | APPLICANT |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| CofO in Progress | 8/3/2021 | MICHAEL TEMPLE |
| CofO Issued | 9/7/2021 | MICHAEL SMITH |
| Permit Finaled | 9/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/7/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/7/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | ADRIAN CASTRO |
| Specific Plan | Cleared | 1/8/2021 | CHRISTINE BUSTILLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/10/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/12/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 3/16/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/22/2021 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 4/8/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/15/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 4/15/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/4/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/4/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 5/4/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 5/4/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 5/11/2021 | Approved | THOMAS FINNILA |
| Insulation | 5/18/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 5/27/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/14/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 7/14/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 7/14/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/29/2021 | Approved | VINCENT HANLEY |
| Final | 7/29/2021 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 7/29/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 7/29/2021 | Approved | VINCENT HANLEY |
| MERV13>=Final | 7/29/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/29/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Gas Company | VINCENT HANLEY |
| Smoke Detectors | 7/29/2021 | Approved | VINCENT HANLEY |
| Final | 8/3/2021 | OK to Issue CofO | MICHAEL TEMPLE |