6327 1/2 W 6TH ST 90048

Certificate Information: 6327 1/2 W 6TH ST 90048

Application / Permit
20016-10000-32244
Plan Check / Job No.
B20LA23163
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF DETACHED GARGAE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)&(d). All work per Wood Frame Prescriptive Design.
Permit Issued
Issued on 7/19/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/22/2020 ZAW HAN
Corrections Issued 1/5/2021 ZAW HAN
Applicant returned to address corrections 8/20/2021 ZAW HAN
Applicant returned to address corrections 4/21/2022 LUKE GONZALES
Building Plans Picked Up 4/22/2022 APPLICANT
Plan Check Approved 7/19/2022 CHRISTOPHER KOMANCHECK
Issued 7/19/2022 APPLICANT
CofO in Progress 9/12/2022 ANDREW NAVE
CofO in Progress 9/28/2022 ANDREW NAVE
Permit Finaled 10/5/2022 DANIEL ORRANTE
CofO Issued 10/5/2022 DANIEL ORRANTE
Permit Finaled 10/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 8/17/2021 MAXFIELD VERMY
Address approval Cleared 8/19/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/19/2021 RENZ SORIANO
Sewer availability Cleared 8/19/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/9/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 1/12/2022 RICARDO BOHORQUEZ
Construction near power lines Cleared 4/13/2022 RIDWAN HARDY

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/25/2022 Approved EVAN COOPER
ELECTRICAL-Final 7/25/2022 Corrections Issued EVAN COOPER
Final 7/25/2022 Corrections Issued EVAN COOPER
HVAC-Final 7/25/2022 Corrections Issued EVAN COOPER
METHANE-Final 7/25/2022 Approved EVAN COOPER
METHANE-Rough 7/25/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 7/25/2022 Not Ready for Inspection EVAN COOPER
Final 8/12/2022 Not Ready for Inspection EVAN COOPER
Smoke Detectors 8/12/2022 Approved EVAN COOPER
Final 9/12/2022 OK to Issue CofO ANDREW NAVE